Bar bending schedule shows the details of reinforcement for
dia of the bar, cutting lenght of the rod, bending details
etc for a particular member.
Is This Answer Correct ? | 31 Yes | 0 No |
Answer / sjtbehera
yes. the bar bending schedule shows the cutting length. and
shape of bar of a structure.
Is This Answer Correct ? | 9 Yes | 0 No |
Answer / guest
bar bending schedule is useful for bar bender (fitter) for
cutting & bending of steel
and working of quantity of steel in building
Is This Answer Correct ? | 5 Yes | 0 No |
BBS = Bar Bending Schedule
uses:
1)provides details of Different Diameter of Steel.
2)Provide the Cutting Length
3)Details of Bar shape
4)Total LEngth
5)Weight of Bar
6)Total Qty of Steel used
7) BBS is used for Billing work
Is This Answer Correct ? | 4 Yes | 0 No |
Answer / fezan butt
BBS is the name of calculate the total wt.of steel as per
drawing i/c cutting,bending overlapping etc
Is This Answer Correct ? | 1 Yes | 0 No |
How much Pressure will apply in Water proofing Grouting method to fill the crack in beams or slabs?
How much concreat we make by 1 bag cement? (ratio- 1:1.5:3 or 1:2:4)
2 Answers Castles Consulting Engineers, KCP, Opaque Infrastructure,
1) why bent up are provided at l/4 or l/5 distance not at l/8or l/10? 2) why extras are provided in beams at top and why upto 0.3l distance max.? 3) why chairs are provided in two way slab?
can i place column steel lapping in floor beam? my lapping is 24 inches in floor beam and 24 inches on floor beam
what is mean by Face bar using in coloums?
What height of a 3.5 m high 300 x300 mm proposed col. can be casted at a time ?
what is the bend correction for 90 degree of bend in any dia of HYSD steel reinforcement as per IS code ?
use ofr concrete as per grade ?
weight rcc m30
Can compresive strength test for concrete at 1 day age possible to carry out? If yes, which IS code describes the procedure for such testing?
How to calculate quantity of cement , sand and granite from concrete mix ratio and volume of work
If we don't have drawing for Excavation of building,At what rule we will go for excavation and how much depth will go for a villa?