how to calculate the steel quantity for beams & columns also footing net? what is the formula..

Answer / sachin

TO calculate the steel qty first calculate the length of
steel as per drwg and multiply this length of steel to the
per meter wt. of the respective dia of steel. THIS GIVES
THE WT. OF STEEL IN KG.

100.3 plinth level indicates the RL of the plinth beam with
respect to the BM fixed for the plot plan.

Is This Answer Correct ?    32 Yes 10 No

how to calculate the steel quantity for beams & columns also footing net? what is the formula..

Answer / ijaz

weight of any thing can be calculated by formula
wight= unit weight x volume

Is This Answer Correct ?    6 Yes 5 No

how to calculate the steel quantity for beams & columns also footing net? what is the formula..

Answer / vittalanand

0.089 % of concrete is requirement of steel

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

In cement concrete pavements why cracks are develop aolng with logitudinal&tangenteal directions

5 Answers   L&T,


What are your goals?

1 Answers   Cisco, Flextronics, Hexaware,


WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?

0 Answers  


HOW we can calculate the quantity of sand and cement for 1:4 plastering with a thickness of 12 mm..total area need to be plaster is 985 sqm

5 Answers  


what is formula for concrete mix ratio in m20, m25 and m30?

2 Answers   Reddy Veeranna Constructions,






what is workability,define it?

1 Answers  


what is correct temperature for pouring concrete?

3 Answers   L&T,


How much overlapping required for welding the reinforcement bars in Columns & beams

3 Answers  


what are the strenth of 1cum brick work

5 Answers  


why distibuters used in rcc slsb

4 Answers  


how to calculate the value of 162?

2 Answers   GKC Projects Limited GKCPL, L&T, OPG,


advantages & disadvantages of using crusher dust instead of sand in r.c.c work

3 Answers   L&T, Shm Consultants,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)