we all know that corona is nothing but ionization of air around
the conductor and there by allowing current to pass through
ionized air.but we are not getting any short circuit in between
the respective phases though the air turned as a conductive media
between them??
Answer / raghavendran
In corona, the air around the conductor(phase) is ionized
and starts conducting.But the potential build up between any
two conductors is not higher than the break down strength of
insulation of air.The clearance between the two conductors
is designed keeping this fact is mind.Hence it do not get
short circuited.May be if the clearance is small, there
might be any possibility of Short circuit.
| Is This Answer Correct ? | 19 Yes | 0 No |
in star connected 4wired transmission system ,what happen if the neutral is grounded . or not grounded. which is significant and y
i want to measure voltage difference between neutral and earth so i just simply use voltmeter. my question is that may i use this measure continuosly.or there are some electricity board restrication on that? or it creat some problem on my measuring device..?
WHY CURRENT DECREASES WHEN VOLTAGE IS INCREASED IN A CURRENT TRANSFORMER ?
Explain the operation carried out in thermal power stations?
What is the role and reponsibilities of Electrical Engineers in construction field?
12 Answers ETA, Garg Electronics, L&T,
What are the no-load losses for the 11000/415V transformer with the following rated capacity? 1.1500 kVA 2. 2000 kVA 3. 2500 kVA 4. 3000 kVA
why in a swquence network representation, the negetive sequence generated voltage is taken as zero?
What will happen if 33 kv is given to a 11/0.415 kv Distribution transformer?
WHAT IS THE DIFFERENCE BETWEEN RESISANTANCE AND IMPEDANCE IF IMPEDANCE IS MORE THAN RESISTANCE AT SAME VOLTAGE CAN WE HAVE RELATION DERIEVED BETWEEN THEM
WHY DIODE IS CONNECTING ACROSS SWITCHES
What should be the Sandwitch type Al. bus bar capacity for 2 M.W.Gen. set, having continuous full load current- 3463 Amps,ambient temp.- 50 Deg. C., Required temp. raise-20 deg.C., it will run 24 hrs, 365 days on full load, required highly reliable.
We are installing a 1.6 MVA transformer at our crusher plant and the feeder of HPSEBL is 2 km away at substaion . and a VCB is installed in the substaion which is 2 km away from transformer so we need another VCB near the transformer.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)