what"s the responsibilities for QC(quality controler)in high
rise buildings?
Answers were Sorted based on User's Feedback
Answer / n c pathan
The answer can not be given in one line. QC Engineer has
lot of responsibilities. It involves mainly quality of
materials and quality of workmanship. He has to see that
work is being executed in accordance with the
specifications laid down in the contract. In order to
achieve over all quality he has to maintain record of cube
testing of concrete, test results of steel and other
construction material at site.
Is This Answer Correct ? | 29 Yes | 0 No |
Answer / deepak
To Check the Quality work at each stage as per IS Code or the Vendor Methodology
Is This Answer Correct ? | 10 Yes | 2 No |
Answer / raghavendra
The QC engineer ensures the work is carried out according
to the project contract specifications,project quality plan
(PQP),inspection and test plan(ITP)....He is also
responsible for timely reporting of any non-comformance,un-
approved material usage etc. etc.
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / ksrao
Inspection of works three 3 stages
Pre construction : input materials testing
During construction : cocrete- w/c ratio cubes casting ,Brick work - proportion of cm,joints etc
Post construction:finishings, levels,testing of strengths with CTM,core cutter,NDT tests
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / ksrao
Monitoring all the works stage wise maintaining
ITP,QAP,QMP and maintaining all records related to QC.
Is This Answer Correct ? | 0 Yes | 0 No |
what is the weight of concrete cube of 1ft*1ft*1ft? tell me weight in pound & in KG
what is shuttering co efficient?
What is the tensile strength of wood?
How to convert N/MM2 TO KG/CM2
how much quantity of water is required for main wall brick work, partition wall brick work,and for internal and external plastering and how it is calculated?
1 Answers LiveCon, Sobha Developers,
What is the outturn of Ceiling plastering
How can we convert weight batch to volume batch for m30 mix
what is the procedure involved in preparing mix design of m15 grade as per IS-10262-1982
if water absorption is more than 25 percent in brick, what is the defect in it?
what is pile foundation?
How we can calculate the quantity of sand, & cement, & also aggregate for a slab. Length 25'/3.28 = 7.62 Mtr width 20'/3.28 = 6.09 Mtr depth 6" /3.28 = 0.152 Mtr
what do you mean by yeild stress of a material? What will happen when hit is given to cement?