What is Time at Large?
Answer / er. abhijit sane
Time is at Large when the project is likely to extend
beyond its dead line. Time is at large when there are
events which adversly affect the execution of the works and
result in dealy.
The delays may be due to deficiencies on part of the
Contractor or Owner
Is This Answer Correct ? | 5 Yes | 1 No |
what isIS code no for preparation of BAR BENDING SHEDULE (BBS)
the capacity of water tank in liters if the diameter is 3m, and maximum height of water level as 1m.
plz tell.. how can we find weight(in kg) of 1 cum of m20 mix..? how can we find the ratio of cement sand and agregate on site i.e if we given some amount of m20 mix then hw we find the ratio..?
give me the mix proportion for design mix concrete M10 grade 1:4:8
13 Answers Gammon, IOCL, PSL, SDG, Simplee, STUP Consultants Pvt Ltd,
role of constituents of cement? how they works
3 Answers BPTP, Gammon, L&T, Totem Infrastructure, Vishwa Infrastructures,
sir, whitch is the best book (writer name) for prepration of gate....
How many square meter can mason layout chb per hour
10x10 slab design
What is geopolymer based concrete?
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
neutral axis more than the critical neutral axis then rainforcement in rcc beam belong to over or under rainforcement
how i can tak Quantity of mortar in block work