what"s the formula to find the quantity (consumption) of
cement,sand,aggregate for 1m3(1:2:4)?
Answers were Sorted based on User's Feedback
Answer / prakash kale
for 1m3 conctre --
Take a 52% added dry surface of concrete
1+.52 = 1.52
i.e.
For 1.52 cu.m. concrete
Then
1.52/1+2+4=1.52/7
=.21714
=.22
so.22/.0354 =6.2 bags(1 bag = .0354 cu.m cement)
6.2 bags/cu.m in 1:2:4
Sand--
.22 x 2 =.44 cu.m.
| Is This Answer Correct ? | 118 Yes | 13 No |
Answer / mrinal kumar brahma
Mix ratio 1(cement):2(sand):4(aggregate)
For 1m3 concrete:
1.51(constant)/(Sum of ratio, i.e 1+2+4=7)=0.216
For cement= 0.216x28.57(constant)=6.2 bag
For sand=0.216x2(sand ratio)=0.43 m3
For aggregate=0.216x4(aggregate ratio)=0.86 m3
| Is This Answer Correct ? | 60 Yes | 10 No |
Answer / vishal rana
Ratio=1:2:4(cement:fine
agg.:coarse agg.)
Sum of the ratio=1+2+4=7.
Total dry mortar for 1cum
cement conc.=1.54(it is fixed)
There for=1.54/7=.22cum
Then quantiy of,cement=.22 into
28.8=6.24 bags.
Sand=.22 into 2(ratio of
sand)=.44cu m.
Aggregate(shingle or bajri)=.22
into 4=.88 cu m.
Materialr for 1cum cement conc.
1:2:4.
Cement=6.24bags
Sand= 0.44cum
Agg.=0.88cum
| Is This Answer Correct ? | 47 Yes | 3 No |
Answer / ajay kumar pal.(j.e)
for finding the total value of
take 1.52/(1+2+4)
=.22
hence total qty of cement .22*1= .22cum
cement= .22/.0354 = 6.2 bags of cement
sand = .22*2 = .44cum
Aggr =.22*4 =.88cum
ANS.
| Is This Answer Correct ? | 17 Yes | 6 No |
Answer / ranjithkumar.t
M15= 1:2:4 (for 1 m^3)
1m^3 = 1440kg, 1 bag = 50 kg
so, 1m^3 bags=1440/50
= 28.8 bags
Cement = 1/7*1.52*28.8
= 6.25 bags
Sand = 2/7*1.52
= 0.434 cubic meter
Aggregate = 4/7*1.52
= 0.868 cubic meter
| Is This Answer Correct ? | 6 Yes | 0 No |
Answer / bhupendra potpose
Consumption & Rate analysis RCC(Cement Concrete) 1:2:4
Providing and placing cement concrete excluding formwork &
reinforcement
1.475 Ref: Always use 1..475 standard
Proportion of materials
(1440 Kg / Cum ) Cement 1
(Dry 1600 Kg / Cum & Wet 1850 Kg /Cum ) Sand
2
(1650 Kg / Cum ) Metal 4
Total 7
Std constant(1.5) / Total of proporttion(7)
0.211
1) Required volume of cement for 1 cum
1 Proportion of cement 0.211
Add wastage 2.50% 0.005
Vol of cement for 1 cum 0.216
0.035 is cum qty of per 50kg of bags, no of bags
0.035 6.171
Cost of cement per bags 325
Total of -1, cost of bags 2005.5
2) Required volume of Sand for 1 cum
2 Proportionof Sand 0.421
Add wastage 2.50% 0.011
Vol of Sand for 1 cum 0.432
Cost of sand per Cum 2125
Total of -2, cost of sand 917.9
3) Required volume of Aggregate for 1 cum
3 Proportionof Metal 0.843
Add wastage 2.50% 0.021
Vol of Metal for 1 cum 0.864
Cost of Metal per cum 975
Total of -3, cost of metal 842.3
A- Total of (1+2+3), cost of Material (Concrete)
3765.8
4)Cost for Manpower ,Mixing ,Shifting & Machinary ,
0.35%
B-Total of -4, Cost of Labour per cum (35%)
13.2
C-Total of (A + B) cost of Material & Labour
3779.0
5) Add Over head if any 5% 188.95
6) Profit 15% 595.19
D- Total of (A+B+C)cost P/A 1:2:4 Concreting
4563.12
| Is This Answer Correct ? | 8 Yes | 4 No |
Answer / gilbertrufino
calculate first the total volume of concrete
1:2:4
for cement = vol. X 9 = ____ bags of 40kg portland cement
for sannd = vol. X 0.5 = ____ m^3
for gravel = vol. X 1.0 = ____ m^3
| Is This Answer Correct ? | 11 Yes | 10 No |
Answer / vigneshwaran s
Generally its easy to find it.
Find Total Parts = (1+2+4)=7 Parts.
For 1 cu.m of concrete the total parts = 1.57
Unit weight of cement = 1440 kgs
Cement = (1440/7)*1.57 = 322.97/50kgs = 6.46bags.
1 bag cement= 1.25cft
Sand = 6.46*1.25 = 8.075 cft*2 =16.15 cft
Aggregate = 8.075 cft*4 =32.3 cft.
Thats all...
Result:
Cement = 6.46 bags
Sand = 16.15 cft
Aggregate = 32.3 cft.
Regards,
Er.Vigneshwaran S
| Is This Answer Correct ? | 5 Yes | 9 No |
what is flashing?
What is the difference in Cement content for M-20 Concrete if y ou use OPC & PPC? What is the difference in the Curing Period?
what is the difference between compaction and consolidation?
give me the mix proportion for design mix concrete M10 grade 1:4:8
13 Answers Gammon, IOCL, PSL, SDG, Simplee, STUP Consultants Pvt Ltd,
Why shear forces are usually neglected in column design?
How to calculate compressive strength of concrete cube dencity
5 Answers Shoba Devlopers, Sobha Developers,
can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?
How much used for sand per square meter in 12mm Thickness
IN CIVIL ENGINEERING DESIGN WHY WE ARE USING LIMIT STATE METHOD IS BEST? I THINK WORKING STRESS METHOD IS BEST? EX; FOR COLOUMN DESIGN IN LIMIT STATE METHOD AST IS;1913SQ.MM SAME TIME WORKING STRESS METHOD IS ;2213. SO I THINK WORKING STRESS METHOD IS VERY STRONG COMPARE THEN LIMIT STATE METHOD? MY OPENING IS CORRECT OR NOT? PLS TO EXPLAIN SIRS
What is HEAVIER? A kilo of SAND OR A kilo of GRAVEL?
CALCULATE QUANTITY OF RCC COLUMN
What is the best mixing ratio of concrete materiloas for raft foundation?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)