Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what"s the formula to find the quantity (consumption) of
cement,sand,aggregate for 1m3(1:2:4)?

Answer Posted / vigneshwaran s

Generally its easy to find it.

Find Total Parts = (1+2+4)=7 Parts.

For 1 cu.m of concrete the total parts = 1.57

Unit weight of cement = 1440 kgs

Cement = (1440/7)*1.57 = 322.97/50kgs = 6.46bags.

1 bag cement= 1.25cft

Sand = 6.46*1.25 = 8.075 cft*2 =16.15 cft

Aggregate = 8.075 cft*4 =32.3 cft.

Thats all...

Result:
Cement = 6.46 bags
Sand = 16.15 cft
Aggregate = 32.3 cft.


Regards,

Er.Vigneshwaran S

Is This Answer Correct ?    5 Yes 9 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the materials used in building a gravity dam?

1122


what is the weight of 12mm aggregates?

1566


What sizes of stones chips are used for foundation, column and floor casting. Please answer in detail.

2114


do we decide reinforcement steel , based on bending moment ? give example with continous slab?

2393


How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097

2272


cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building

2451


Please tell me any one, how many quantity concrete paver block fixing perday ( 8hours) per mason??

1703


2. What are the advantages of your present job, things you like about it?

3133


design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal

2241


What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.

2607


how to take concrete quantity for precast segment for viaduct project?

3116


How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.

4207


In Abutment walls (A1 side) why we are adopting fixed bearing (POT-PTFE)?

2105


indian standard split spoon sampler

1979


What applicable rate of wct in bihar

1851