Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


What height of a 3.5 m high 300 x300 mm proposed col. can
be casted at a time ?

Answers were Sorted based on User's Feedback



What height of a 3.5 m high 300 x300 mm proposed col. can be casted at a time ?..

Answer / sjtbehera

According to IS code In acolumn minimum height of casting
is 1200mm or 4' (apporox)

Is This Answer Correct ?    18 Yes 4 No

What height of a 3.5 m high 300 x300 mm proposed col. can be casted at a time ?..

Answer / kamlesh chauhan

we can not caste any ht more than 2.4 mt at a time,you can
caste only 2.4 mt ht at a time,because vertical drop of
concrete should not be more than 2.4 mt due to seggregation
problem.

Is This Answer Correct ?    17 Yes 9 No

What height of a 3.5 m high 300 x300 mm proposed col. can be casted at a time ?..

Answer / ajeet kumar bhatnagar

As per IS. concrete should not pour more than 1.5mtr hight
but if you are pouring by pump using hose pipe you can fall
concrete up to 1.5mtr height and col.up to 3.0 mtr. height
can be casted.

Is This Answer Correct ?    10 Yes 2 No

What height of a 3.5 m high 300 x300 mm proposed col. can be casted at a time ?..

Answer / ajeet kumar bhatnagar

As per the I.S.code concrete should not pour greater than
1.2 mt heigh. But if u are using hose pipe then u may cast
as per the lenth of hose pipe reaches in side of col,which
also maintains I.S. specification of 1.2 mtr heightpouring
Thus we can cast col. more then 1.2 mtr. height. Generaly
hose pipe may be inserted up to 2.0-2.5 mtr depth in col.
and we can cast up to 3.7 mtr height of col.

Is This Answer Correct ?    5 Yes 0 No

What height of a 3.5 m high 300 x300 mm proposed col. can be casted at a time ?..

Answer / jhulzkee

1.5m since the max drop of concrete should be 1.5m height
to avoid seggregation of aggregates.

Is This Answer Correct ?    2 Yes 0 No

What height of a 3.5 m high 300 x300 mm proposed col. can be casted at a time ?..

Answer / girish rawat

you can cast up to 4 mts of column if you have reqd
supporting system for the same. As for the IS you cannot
pour concrete more than 1.5 mts as segregation and self
compaction takes place. For the columns you there is no
issue as the concrete doesn't drop to the bottom at once. it
is interrupted by stirrups all the way.
This is based in practical experience and we have got it right.
Secondly nowadays there is Mivan Shuttering where you cast
the entire slab and column at one stroke.
Keep moving with new technology, you will save time and the
quality will be better if the mix is homogeneous lesser joints

Is This Answer Correct ?    4 Yes 3 No

What height of a 3.5 m high 300 x300 mm proposed col. can be casted at a time ?..

Answer / satyendra mishra

1.2 mtr.

Is This Answer Correct ?    0 Yes 1 No

What height of a 3.5 m high 300 x300 mm proposed col. can be casted at a time ?..

Answer / anand

7Ft

Is This Answer Correct ?    4 Yes 7 No

Post New Answer

More Civil Engineering Interview Questions

Describe the sections included in a typical bill of quantities

0 Answers  


What is capicity of cap lock scffolding stander(vertical member) and ledger of different size?

0 Answers   Gammon,


What's is mean by survey

1 Answers  


which red: used in roof teping, then use only cement

0 Answers  


What will be the angle for hook in column ring for column size 600x750 mm bar size 10mm for ring

3 Answers  


How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance

0 Answers  


percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters

0 Answers  


Are you a team player?

0 Answers  


What is the correct position of lapping splice of reinforcement steel bars in a beam at top & bottom of the beam?? what is the reason for this location?..what are the factors affecting lapping location in beam?

6 Answers   SPCL,


Adout concrete

1 Answers   Bhel, TATA,


which is higher specific gravity or bulkdensity

2 Answers   ICGAR, IGCAR,


how to calculate of m20 c.c road work 1cu.m

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)