Thirty men take 20 days to complete a job working 9 hours a
day. How many hour a day should 40 men work to complete the job?
(a) 8 hrs
(b) 7 1/2 hrs
(c) 7 hrs
(d) 9 hrs
Answers were Sorted based on User's Feedback
Answer / sneha aitha
30 men-20 days-9 hours
40 men- ? - ?
so m1 d1 h1 = m2 d2 h2
30*20*9 = 40*d2*h2
m1d1=m2d2
30*20=40*d2 then d2=15
30*20*9=40*15*x
so then x=9hrs
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vijayalaxmi uppala
m1*d1=m2*d2
30*9=40**d2
270=40*d2
d2=270/40
d2=6.75
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / praveen
30 * 20 * 9 = 5400 man-hours required to complete the job
Let x = no. hrs a day to do the same job (assuming in 20 days)
40 * 20 * x = 5400
800x = 5400
x = 5400%2F800
x = 6.75 hrs a day for 20 days to do the same job
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / jyosna
30 * 20 * 9 = 5400 man-hours required to complete the job
:
Let x = no. hrs a day to do the same job (assuming in 20 days)
40 * 20 * x = 5400
800x = 5400
x = 5400%2F800
x = 6.75 hrs a day for 20 days to do the same job
SO THE ANSWER IS 7HRS(approx)
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / yashwanth krishna
If the question is "how many hours should 40 men work to complete the same work done by 30 men working 9 hrs a day for 20 days?" then my answer would be,
if 30 men can finish a PIECE OF WORK in 20days then
1man's work will be 1/30for 20days and 1/30*20=1/600 is one man's 1 day work
then 40 men's 1 day's work is 40/600
and 40 men can do the work in 600/40 days=15days(working 9 hours a day)
which is 135hours(15*9)
if the work is to be completed in 20 days then 40 men should work 6.75hrs a day(135/20)
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / rahul parmar
30 x 20 x 9 = 5,400 man hours required for the job
You’ve given us 40 men and 20 days:
5400 / 40 / 20 = 6.75
So they would have to work 6.75 hours a day to complete the job.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / muthuganesan
while increase the men, the working days will be decreased,
but the working hours would be the same, nobody decrease the
working hour in their organization.
so answer would be a) 9 hrs
| Is This Answer Correct ? | 1 Yes | 3 No |
Answer / gajendra
30*20*9=40*20*T2
t2=(3*9)/4=6.75=7
so currect answer is 7.
| Is This Answer Correct ? | 4 Yes | 10 No |
Answer / fox
they should still work 9hr days and get the job done
quicker!
| Is This Answer Correct ? | 9 Yes | 41 No |
A ship went on a voyage.After it had travelled 180 miles a plane statrted with 10 times the speed of the ship. An army 50 miles long marches at a constant rate. A courier standing at the rear moves forward and delivers the message to the first person and then turns back and reaches the rear of the army as the army completes 50 miles. Find the distance travelled by the courier.
Given that April 1 is tuesday. A, B, C are 3 persons told that their farewell party was on � A - May 8, thursday � B - May 10,tuesday � C - June 5, friday Out of A, B, C only one made a completetly true statement concerning date,day and month The other told two one told the day right and the other the date right.. What is correct date, month, day.
In a certain college, 20% of the boys and 40% of the girls attended the annual college outing. If 35% of all the students are boys, what percent of all the employees went to the outing?
which one is different in below numbers? 352,792,462,583,475
there was a swimming pool of squre shape and it is having four trees at four ends....how to double the size of swimming pool without cutting the trees...?
ram sita hai ,to sita kaun hai?
Dear sir,i'm siva.i have applied for rrb ASM.please send last 5 years Aptitude Question paper with answers.thanks.regards siva.
What amount of compound interest can be obtained on an amount of Rs. 4500 at the rate of 4% p.a. at the end of 2 years?
A cube is coloured red on one face,green on the opposite face,yellow on the another face and blue on a face adjecent to yellow face. The other two faces are left uncoloured. it is then cut into 125 smaller cubes of equal size. Q-1: How many Cubes are coloured blue on one faces,red or green on another face and have four uncoloured faces? Q-2: How many cubes are coloured red on one face,and have the remaining faces uncoloured?
5 Answers AJ, Dunnhumby, Satyam, SSB,
If 5/2 artists make 5/2 paintings using 5/2 canvases in 5/2 days then how many artists r required to make 25 paintings using 25 canvases in 25 days?
17 Answers Caritor, Infosys, TCS,
In a certain code language DESERT is written RTSEDE. How will the word FAULTS the written in that code language? (a) TSULFA (b) AFLUST (c) LUAFST (d) UAFSTL (e) None of these
15 software functions are there. It is known that atleast 5 of the m are defective. What is the probability that if three functions are chosen and tested, no errors are uncovered.