Thirty men take 20 days to complete a job working 9 hours a
day. How many hour a day should 40 men work to complete the job?

(a) 8 hrs
(b) 7 1/2 hrs
(c) 7 hrs
(d) 9 hrs

Answers were Sorted based on User's Feedback



Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / guest

7 1/2 hrs

Is This Answer Correct ?    182 Yes 75 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / mv jaysheelan

(30Men x 20days x 9hrs)/(40Men) = 135 hrs per day. Which
is impossible. So, the answer is none.

Since the question is vague, if you don't answer this
question you may be given mark for this question.

The question should have been

1. How many days 40 men working 9 hrs a day will take to
complete the work.
Answer: (30Men x 20days x 9hrs)/(40Men x 9 hrs) = 15days

2. How many hours a day should 40 men work for 20days will
take to complete the work.
Answer: (30hrs x 20day x 9hrs)/(40Men x 20days)=6 3/4 hrs

Is This Answer Correct ?    122 Yes 34 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / venkatesh prabhu.g

30*20*9=40*20*x
(3*9)\4=x
6.7hrs

Is This Answer Correct ?    104 Yes 41 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / dhanaraj

days is eqaul....
so calculte power and time..
power 30 hour 9
power 40 hour x
40x=30*9
x=270/40
x=6.75
x=6 3/4

Is This Answer Correct ?    56 Yes 11 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / herry

27/4 hours Per Day Is Foll and Final Answer

Is This Answer Correct ?    56 Yes 27 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / vidya

In both cases days are same
so
m1*ti=m2*t2
30*9=40*t2
t2=270/40=71/2

Is This Answer Correct ?    213 Yes 192 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / vishal pitaliya

30*20*9=40*20*x

x= (30*20*9)/(40*20)

x= 27/4

x=6 3/4 hrs answer

Is This Answer Correct ?    31 Yes 10 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / suratnarayan tripathi

30*20*9=40*20*x
600*9=800*x
5400=800*x
x=5400/800
x=54/8
x=27/4 Hours
x=6.75 hours

It means
x=7 hour and 15 minutes

Is This Answer Correct ?    30 Yes 19 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / sumit sourabh

‎40 men work 6 hours 45 minutes a day for 20 days to complete the job...........

AS WE SEE
(30*20*9)=(40*20*H)
5400=800 * H
H = 6.75 HOURS
I.E; 6 HOURS 45 MINUTES IS THE WORK DONE PER DAY

Is This Answer Correct ?    9 Yes 2 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / baddy

equation given: 30 x 9 = 40 x X
=> X = 30 x 9 /40
=270/40
= 6.75
= 6 hrs and 45 mins

So,Ans is
6.75 hrs

Is This Answer Correct ?    5 Yes 0 No

Post New Answer

More General Aptitude Interview Questions

Light glows for every 13 seconds . How many times did it between 1:57:58 and 3:20:47 am

0 Answers   InfoTest,


Argentina had football team of 22 player of which captain is from Brazilian team and goalki from European team. For remainig palayer they have picked 6 from argentinan and 14 from european. Now for a team of 11 they must have goalki and captain so out of 9 now they plan to select 3 from rgentinian and 6 from European. Find out no. of methods avilable for it.

2 Answers   CTS,


A bus started from bustand at 8.00am, and after staying for 30 minutes at a destination, it returned back busstand. The destination is 27 miles from the busstand. The speed of the bus is 18mph. During the return journey bus travels with 50% faster speed.At what time does it return to the busstand?

0 Answers   TCS,


An article sold at a profit of 20% if both the cost price and selling price would be Rs.20/- the profit would be 10% more. What is the cost price of that article?

0 Answers   3i Infotech, Amazon, Canara Bank,


In a certain code, TERMINAL is written as SDQIJOBM. How is CREDIBLE written in that code? (a) BQDCJCMF (b) DSFEJCMF (c) BQDCHAKD (d) DSFEHAKD (e) None of these

9 Answers  






Also could u send me the model question paper for exam of Economics & Stastics dept. of maharashtra

0 Answers  


if a ball is dropped from 8 meter and it bounce back half the distance then what is the distance it travel before going to rest?

8 Answers   CTS, Dolat Capital,


Which team won the National Football League this year?

1 Answers   RRB,


The average score of a cricketer for 13 matches is 42 runs. If his average score for the first 5 matches is 54, then what was his average score (in runs) for last 8 matches?

0 Answers  


k, l are men who take home a salary of x, y respectively.the total amount taken home is

0 Answers   TATA,


the concession stand at cinema city sells popcorn in three sizes-large,super and jumbo one day cinema city 240 bags of popcorn and the ratio of large and super to jumbo was 8:17:5.how many super bags of popcorn were sold on that day

3 Answers  


Shortcut keys in excel : Ctrl + k Ctrl + d Ctrl + y

5 Answers   eClerx,


Categories