The project manager is working with the team to help them
understand the constraints the project must operate within.
As a kick off to the meeting, the manager displays the
first slide, which reads: Scope, Schedule and Budget--You
may pick two.
Based on the above scenario, which one of the project
concepts is the manager relating to the team?
Answers were Sorted based on User's Feedback
Answer / sreenivas.p.s
It should be Scope and Schedule should be the concepts
which the manager relates to the team becouse were as
Budget is concern is related to Project Manager only not to
the team
Is This Answer Correct ? | 4 Yes | 2 No |
when doing regression testing, how can we know that other screen or module are affected?
what is system testing? explain with an example.
Give an example of high severity and low priority bug?
What are the testing processes after getting SRS to tester?
What is limitation of v shaped model
What are the Test case for the file transfer.
what is differnce between QC @ QA , test strategy, very urgent pls
One scenario: yahoo inbox doesnt show emails but instead of all inbox emails are shown in draft folder. How do u wrte the defect repert for this scenario.
What is QA and QC ? Tester's are coming under QA or QC ?
Write four good test cases on refill ball pen?
How Requirement is linked with traceability matrix. Give proper example
For a functionality we have 20 test cases, among 20 testcases 15 of them are Passed and 5 Failed. How will you report to your Manager ? Does the functionality passed or failed or partial passed/failed ??