Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


You have been asked to submit a proposal for a project that has been put out for bid. Prior to submitting the proposal, your company must register so that their firm is on the qualified seller list. Which of the following is true?
A. The qualified seller list provides information about the sellers and is a tool and technique of the Solicitation process.
B. The qualified seller list provides information about the project and the company that wrote the RFP and is an input to the Solicitation process.
C. The qualified seller list provides information about the project and the company that wrote the RFP and is a tool and technique of the Source Selection process.
D. The qualified seller list provides information about the sellers and is an input to the Solicitation process.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

how many chart of a/cs can assign to company code?

1 Answers  


What change would you like to bring in the management of your previous organization ?

0 Answers   EX,


You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the scope statement for your new Natural Bug Busters project. A key stakeholder has informed you that a deliverable is missing from the scope statement. This deliverable is a critical success factor. You should do which of the following? A. Inform the stakeholder that work not stated in the scope statement is excluded from the project. B. Modify the scope statement to reflect the new deliverable. C. Inform the stakeholder that this deliverable can be included in the next project since sign-off has already been obtained. D. Modify the scope statement after an approved change request has been received from the stakeholder.

0 Answers  


HI everyone, I am commerce graduate, completed MBA Finance in Distinction. I would like to do FI/CO. Could any one of you please suggest, which is the best instistute for FI/CO training in Hyderabad. Compulearn, Reliance, or other. Thanks in advance Rupa Gupta

4 Answers  


What are the characteristics of management?

0 Answers   Mahatma Gandhi University,


You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following is true? A. This is the result of working with teams of people from two different countries. B. This condition is known as culture shock. C. This is the result of jet lag and travel fatigue. D. This condition is known as global culturalism.

0 Answers  


What is the concept of project management?

0 Answers  


All of the following are true regarding the project plan except: A. Some of its inputs are outputs from other Planning processes. B. It's used to guide the project executing and controlling processes and is the baseline used to measure project performance. C. It consists of one document that should be formally approved and signed by stakeholders. D. It contains things like the WBS, project schedule, and resource assignments.

0 Answers  


Describe size oriented metrics.

0 Answers  


The VP of marketing approaches you and requests that you change the visitor logon screen on the company’s website to include a username with at least six characters. This is considered: A. Project initiation B. Ongoing operations C. A project D. Project execution

1 Answers  


All of the following are true regarding configuration management except: A. Requires all acceptance decisions to be made through the CCB B. Serves as a change control system C. Describes the physical characteristics of the product of the project D. Controls changes to the characteristics of an item or system

0 Answers  


When a project is being performed under contract, the product description is provided by which of the following? A. The buyer B. The project sponsor C. The project manager D. The contractor

0 Answers  


Categories