Suppose you did all your work in a 32 bit system, the
production server is 64 bit system, you find that during
UAT, the system fails and is not working, how will u
communicate to your customer, what solution will you
provide to the client?

Answers were Sorted based on User's Feedback



Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / bj

Check back with your specifications regarding the server
requirements. If the requirement was never specified, you
have assumed that the requirement is a 32 bit system.

In this situation, list the possible reasons why it failed.
Run a system test on a 32 bit machine and doubly ensure that
the reason for failure in only the server specification

Schedule a meeting with the customer and let them know that
the UAT failed and the most probable reason being he server
specification. Provide them the list of other possible
reasons (if you found any) and also inform them about your
plans on how to plan to tackle the issue and your
guesstimate of the time for the same.

Based on the criticallity of the system, one of the
solutions could be to deploy the software system on a 32 bit
server while you figure out a way to fix the issue. This
option could be given to the customer.

It is quite possible that the customer would take this
option and this would save time for the customer and help
your team to quickly find a fix.

Otherwise go with whatever the customer thinks you should do.

Is This Answer Correct ?    19 Yes 0 No

Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / veerendra kumar

First of all we need to react to this situation more in a
technical way, many of the 64 bit OS are supporting 32 bit
applications. First verify if the OS can support 32 bit app
on the UAT or PROD server, 99% OS would have drivers to run
32 bit apps.

In the worst situation you may go with 32 bit system till
your app gets covert on to 64 bit.

Is This Answer Correct ?    5 Yes 4 No

Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / yogesh

There is not a signle answer for this situation , I faced
this problem , and faced critisim also. I changed the
process steps as part of the reaction.

Assumptions are the most critical factors when PM work out
the planning stage.

As PM it should have been noticed in requirement and test
case reviews about the various platform compatibility
checks.

But this requirement missed totally, in this case,estimate
and negoiate with the customer and ask for the new time
lines for phase by phase migration to 64 bit platform.
Mostly the impact will be on projct cost and who will be
accounted for.

Is This Answer Correct ?    1 Yes 0 No

Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / sreedhara

First Analyze the problem throughly, it is technical problem or requirements mismatch problem or your team developed in 32 bit environment. First test a sample code on the 64 bit environment at development box and ensure it runs with out problem. Then estimate who much extra efforts are required to complete conversion, can we do in module wise or drops (agile method), finalize all these things at your end then approach the customer about the issue, with all the solutions and efforts. Before that ensue that all these things are not captured in the issue log (issues, risks & assumptions).

Is This Answer Correct ?    0 Yes 3 No

Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / shri

having 1 round of testing on 64 bit environment

Is This Answer Correct ?    0 Yes 4 No

Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / ck

First list out the possible reasons why it is failed and
also list out possible solutions...Then inform the customer
with effort required if possible with revised dates

Is This Answer Correct ?    0 Yes 7 No

Post New Answer

More Project Management Interview Questions

All of the following are true regarding configuration management except: A. Requires all acceptance decisions to be made through the CCB B. Serves as a change control system C. Describes the physical characteristics of the product of the project D. Controls changes to the characteristics of an item or system

0 Answers  


What are the functions of project management tool?

0 Answers  


According to the Guide to the PMBOK, the project manager is identified and assigned during which process? A. As an input to the Initiation process B. As an input to the Planning process C. As an output of the Initiation process D. As an output of the Scope Planning process

0 Answers  


You are a project manager for Uncle Sam's Flag Company. Your company has designed a new line of products featuring the American flag. Due to some unique circumstances, the products are in hot demand and the project sponsor has asked you to do whatever it takes to get this project completed early and make the products available. You are to add resources to the project. The sponsor agrees to pay the additional costs since time is now a critical factor. Which technique have you used? A. Crashing B. Resource leveling C. Fast tracking D. Resource loading

0 Answers  


Procurement audits review what? A. The procurement process from Procurement Planning through Contract Administration B. The contract administration process from Solicitation Planning through Contract Administration C. The procurement process from Procurement Planning through Contract Closeout D. The contract administration process from Solicitation Planning through Contract Closeout

0 Answers  






Your project is in the Scope Definition process. You've just completed the WBS. Which of the following is true? A. The WBS breaks the project deliverables down to a level where alternatives identification can be used to determine how level two assignments should be made. B. The WBS breaks the project deliverables down to a level where project constraints and assumptions can be easily identified. C. The WBS breaks the project deliverables down to the work package level where product analysis can be documented. D. The WBS breaks the project deliverables down to the work package level where cost and time estimates can be easily determined and quality control measurements can be determined.

0 Answers  


The purpose of the Initiation process is to: A. Formally recognize the existence of a project or project phase B. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technological advances, or legal requirements C. Formally recognize the stakeholders of the project and identify them in the project charter D. Formally recognize the project sponsor and document his or her project goals

0 Answers  


You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite sometime and are in the performing stage of Team Development. A new member has been introduced to the team. Which of the following is true? A. The Team Development process will start all over again with the storming stage. B. The team will continue in the performing stage. C. The Team Development process will start all over again with the forming stage. D. The team will start all over again at the storming stage but quickly progress to the performing stage. ?

0 Answers  


You work for a large manufacturing plant. You're in the Initiation process of a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following actions should the project manager take? A. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend the project proceed. B. The project manager should document the project's goals and known deliverables in a high-level overview document and assume the project is a go. C. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend a feasibility study be performed. D. The project manager should document the project's goals and known deliverables in a high-level overview document and deliver it to the stakeholders.

0 Answers  


You are a project manager who has recently held a project team kickoff meeting where all the team members were formally introduced to each other. Some of the team members know each other from other projects and have been working with you for the past 3 weeks during the Planning processes. Which of the following is true? A. Team building begins once all the members of the team are identified and introduced to each other. This team is in the storming stage of Team Development. B. Team building begins at the Planning process. This team is in the storming stage of Team Development. C. Team building begins once all the members of the team are identified and introduced to each other. This team is in the forming stage of Team Development. D. Team building begins at the Planning process. This team is in the forming stage of Team Development.

0 Answers  


You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You've published the scope statement and scope management plan. The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and how the information should be stored and filed is which of the following? A. Scope management plan B. Communications management plan C. Information distribution plan D. Project charter

0 Answers  


All of the following are true regarding parametric modeling except: A. It's a form of top-down estimating. B. It's a mathematical model. C. It's a tool used to estimate project costs. D. It's a tool used to estimate project time.

0 Answers  


Categories