Suppose you did all your work in a 32 bit system, the
production server is 64 bit system, you find that during
UAT, the system fails and is not working, how will u
communicate to your customer, what solution will you
provide to the client?
Answers were Sorted based on User's Feedback
Answer / bj
Check back with your specifications regarding the server
requirements. If the requirement was never specified, you
have assumed that the requirement is a 32 bit system.
In this situation, list the possible reasons why it failed.
Run a system test on a 32 bit machine and doubly ensure that
the reason for failure in only the server specification
Schedule a meeting with the customer and let them know that
the UAT failed and the most probable reason being he server
specification. Provide them the list of other possible
reasons (if you found any) and also inform them about your
plans on how to plan to tackle the issue and your
guesstimate of the time for the same.
Based on the criticallity of the system, one of the
solutions could be to deploy the software system on a 32 bit
server while you figure out a way to fix the issue. This
option could be given to the customer.
It is quite possible that the customer would take this
option and this would save time for the customer and help
your team to quickly find a fix.
Otherwise go with whatever the customer thinks you should do.
| Is This Answer Correct ? | 19 Yes | 0 No |
Answer / veerendra kumar
First of all we need to react to this situation more in a
technical way, many of the 64 bit OS are supporting 32 bit
applications. First verify if the OS can support 32 bit app
on the UAT or PROD server, 99% OS would have drivers to run
32 bit apps.
In the worst situation you may go with 32 bit system till
your app gets covert on to 64 bit.
| Is This Answer Correct ? | 5 Yes | 4 No |
Answer / yogesh
There is not a signle answer for this situation , I faced
this problem , and faced critisim also. I changed the
process steps as part of the reaction.
Assumptions are the most critical factors when PM work out
the planning stage.
As PM it should have been noticed in requirement and test
case reviews about the various platform compatibility
checks.
But this requirement missed totally, in this case,estimate
and negoiate with the customer and ask for the new time
lines for phase by phase migration to 64 bit platform.
Mostly the impact will be on projct cost and who will be
accounted for.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / sreedhara
First Analyze the problem throughly, it is technical problem or requirements mismatch problem or your team developed in 32 bit environment. First test a sample code on the 64 bit environment at development box and ensure it runs with out problem. Then estimate who much extra efforts are required to complete conversion, can we do in module wise or drops (agile method), finalize all these things at your end then approach the customer about the issue, with all the solutions and efforts. Before that ensue that all these things are not captured in the issue log (issues, risks & assumptions).
| Is This Answer Correct ? | 0 Yes | 3 No |
Answer / ck
First list out the possible reasons why it is failed and
also list out possible solutions...Then inform the customer
with effort required if possible with revised dates
| Is This Answer Correct ? | 0 Yes | 7 No |
Which of the following processes assess the likelihood of risk occurrences and their consequences using numeric probability assignments? A. Qualitative Risk Analysis B. Risk Identification C. Quantitative Risk Analysis D. Risk Response Planning
What is the difference between risk impact and risk probability?
All of the following are true regarding the Executing processes except: A. Executing has one core process. B. The majority of the project budget is spent here. C. The greatest conflicts are schedule conflicts. D. Project performance is measured to identify variances.
What are the skills required to be a project manager? Followup question, Rate yourself in each of the skill with examples.
18 Answers Cognizant, Microsoft,
You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You are working on the WBS. The finance manager has given you a numbering system to assign to the WBS. Which of the following is true? A. The numbering system is a unique identifier known as the code of accounts, which is used to track the costs of the WBS elements. B. The numbering system is a unique identifier known as the WBS dictionary, which is used to track the descriptions of individual work elements. C. The numbering system is a unique identifier known as the code of accounts, which is used to track time and resource assignments for individual work elements. D. The numbering system is a unique identifier known as the WBS dictionary, which is used to assign quality control codes to the individual work elements. ?
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and know that you should document: A. Lessons learned B. Performance measurements C. Formal acceptance D. Product verification
Your company, Kick That Ball Sports, has appointed you project manager for their new Cricket product line introduction. This is a national effort, and all the retail stores across the country need to have the new products on the shelves before the media advertising blitz begins. The product line involves three new products, some with multiple deliverables. You are ready to create the WBS. Which of the following is true? A. The WBS should include the three new products and the advertising campaign as level two deliverables. B. The WBS should include the three new products as level two deliverables. C. The WBS should include the three new products as level two deliverables and the advertising campaign as a level three deliverable. D. The WBS should include the three new products and the advertising campaign as level three deliverables.
How do you communicate bad news in your team?
The primary function of the Closing process is to: A. Formalize lessons learned and distribute this information to project participants B. Perform audits to verify the project results against the project requirements C. Formalize project completion and disseminate this information to project participants D. Perform post-implementation audits to document project successes and failures
You are a project manager who believes people will always perform at their best if given the proper expectations and motivation. Which theory do you subscribe to? A. Theory X B. Hygiene theory C. Contingency theory D. Theory Y
During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.
Which of the following is true regarding Administrative Closure? A. It occurs at the end of a project phase and at the end of the project. B. It occurs at the end of the project phase only. C. It occurs at the end of the project only. D. It is performed prior to Contract Closeout.