Which of the following compression techniques increases risk?
A. Crashing
B. Resource leveling
C. Fast tracking
D. Lead and lag
No Answer is Posted For this Question
Be the First to Post Answer
You are working on a project and are in the Quality Planning process. You know that if the customer requirements are not satisfied while the product is still in the control of the organization, it may result in corrective action, rework, scrapping, and downtime. Which of the following is true regarding the cost of quality? A. Cost of quality is an output of this process, and this is an internal failure cost. B. Cost of quality is a tool and technique of this process, and this is a prevention cost. C. Cost of quality is an output of this process, and this is a prevention cost. D. Cost of quality is a tool and technique of this process, and this is an internal failure cost.
Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects
All of the following are true regarding the ADM method except: A. It's a tool and technique of Activity Sequencing. B. It uses one time estimate to determine durations. C. It's also called AOA. D. It's rarely used today.
Which of the following might require rebaselining of the cost baseline? A. Corrective action B. Revised cost estimates C. Updates to the cost management plan D. Budget updates
You are the project manager for a construction company that is building a new city and county office building in your city. Your CCB recently approved a scope change. You know that scope change might come about as a result of all of the following except: A. Schedule revisions B. Product scope change C. Changes to the agreed-upon WBS D. Changes to the project requirements
Describe the risk in software engineering.
What are the qualities of a good project manager?
How a project is made and deliverd to client? please put all detailed steps internally?
what do you do after a milestone is completed?
You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower's site. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What do you know about this project? A. The EAC is a positive number, which means the project will finish under budget. B. You do not have enough information to calculate CPI. C. The CV is a negative number in this case, which means you've spent less than what you planned as of the measurement date. D. The CV is a positive number in this case, which means you're under budget as of the measurement date.
What is triple constraint triangle in project management?
Scope definition is necessary for all of the following reasons except: A. To subdivide project deliverables into smaller components B. To assess the stability of the project scope C. To facilitate time and cost estimates D. To facilitate responsibility and assignment