what is a project management?
Answers were Sorted based on User's Feedback
Answer / hardik
Project management is the discipline of planning,
organizing and managing resources to bring about the
successful completion of specific project goals and
objectives.
| Is This Answer Correct ? | 68 Yes | 6 No |
Answer / pramod pudur
Project Management is the application of knowledge, skills,
tools and techniques to project the activities to meet the
project requirements.
Project management is accomplished through the appropriate
application and integration of 42 logically grouped project
management processes comprising of 5 process groups
(Initiation, Planning, Execution, Monitoring and Control
and Closing)
| Is This Answer Correct ? | 43 Yes | 7 No |
Answer / ganga reddy
Project management is planning & monitoring the task as
per the requriemts and make them complete on time and with
in budget to get desired results.it plays a major role in
organisation build.
| Is This Answer Correct ? | 28 Yes | 7 No |
Answer / sanjay
In theory Project Management is all about initiating,
planning, monitoring, tracking and taking the project to
closure with a desired quality, within budget and in pre-
defined timeline.
In reality, it is all about negotiation, controlling scope
creeps, prioritising and ensuring clear communication
across various stake holders, thereby maintaining the
balance among 3 keys: quality, cost and time.
| Is This Answer Correct ? | 18 Yes | 1 No |
Answer / harish
Project Management is a set of necessary activities
performed to ensure that all the project objectives are met
within the defined parameters of cost, quality and schedule.
It would include everything from starting to executing to
controlling to winding up of the project requiring the
project manager to take care of other parameters like
resource mix, profitability, stake holder communication,
knowledge build up and retention.
As a project manager you might enter a project at any of the
above mentioned phases and exit it at one of the above
stages, but the activities you would need to perform would
be more or less as defined in the above paras.
| Is This Answer Correct ? | 7 Yes | 1 No |
Answer / narayanamurthy
In Simple words it is PDCA(Plan,Do,Check & Act) in the
areas of SSC(Scope,Schedule & Cost Management).
You can find sub-areas for SSC
Which in turn links to
1.Resource Management
2.Communication Management
3.Quality Management
4.Risk Management
5.Change Management
....
| Is This Answer Correct ? | 8 Yes | 2 No |
Answer / nilesh shinde
Project Management can be accomplished by following
oraganisational accepted methodlogy (PMBOK / Prince2) to
deliver project in controlled manner (within set budget
time and quality).
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / jaikumar d
Project management is a methodical approach to planning and
guiding project processes from start to finish. According to
the Project Management Institute, the processes are guided
through five stages: initiation, planning, executing,
controlling, and closing.
| Is This Answer Correct ? | 4 Yes | 4 No |
Answer / guest
Project management means to handle a project within that
duration with that estimated amount.
| Is This Answer Correct ? | 2 Yes | 2 No |
Which of the following is true regarding constraints and assumptions? A. Constraints restrict the actions of the project team, and assumptions are considered true for planning purposes. B. Constraints are considered true for planning purposes, and assumptions limit the options of the project team. C. Constraints consider vendor availability and resource availability to be true for planning purposes. Assumptions limit the project teamwork within predefined budgets or time lines. D. Constraints and assumptions are inputs to the Initiation process. They should be documented, as they will be used throughout the project Planning process.
You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.
All of the following are benefits of meeting quality requirements except: A. An increase in stakeholder satisfaction B. Less rework C. Low turnover D. Higher productivity
You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true? A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline. B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against. C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against. D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.
What is your leadership style?
1 Answers State Bank Of India SBI,
Your hardware vendor left you voicemail saying that a snowstorm in the Midwest will prevent your equipment from arriving on time. You identified a risk response for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy? A. Transference B. Acceptance C. Mitigation D. Avoidance
You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. You are in charge of the network operations part of this project. An important deadline is approaching that depends on the successful completion of the testing phase. You've detected some problems with your hardware in the testing phase and discover that the hardware is not compatible with other network equipment. You take corrective action and exchange the hardware for more compatible equipment. Which of the following is true? A. This is not a corrective action involves human resources, not project resources. B. Corrective action is taken here to make sure the future project outcomes are aligned with the project plan. C. Corrective action is not necessary in this case as the future project outcomes aren't affected. D. Corrective action serves as the change request to authorize exchanging the equipment.
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You have been invited to dinner with the prospective foreign business partners and their spouses upon your arrival. You know that all of the following are generally true except: A. You should spend time building relationships with your prospective foreign business partners before getting down to business. B. You should explain your company's rules, standards, and operating policies at your first meeting with the prospective foreign business partners. C. You should build an atmosphere of mutual trust and cooperation. D. You should respect the cultural differences you'll encounter when working with your prospective foreign business partners.
Which of the following is displayed as an S-curve? A. Gantt B. Cost baseline C. Critical path D. PERT
How to track your team members?
What are the inputs to the Initiation process? A. Product description, strategic plan, project selection criteria, and historical information B. Product description, strategic plan, project overview document, and historical information C. Strategic plan, project overview document, feasibility study, and historical information D. Product description, strategic plan, constraints, and assumptions
The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates