How to calcuate the quantity of cement,sand for plastering 1:4 12mm thick?
Answer / nikita khanadre
Volume of plaster=1m*1m*0.012m=0.012cum
Dry volume=0.012*1.33=0.01596cum
Cement =1/(1+4) *0.01596=0.003192cum/0.035=0.0912 bag
Sand=4/(1+4)*0.01596=0.012768cum
| Is This Answer Correct ? | 2 Yes | 0 No |
How much percentage of silt contain maximum allowed?
Can anyone tell me the salary and job profile of transportation engineers/transport engineer?
1 m^ 3 of concrete 150 x150 mm of spacing of required of steel ?
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
to construct 1450 rft length of 6 feet wall how much cement sand and blocks are required????
when it is noted "JAMB SIM" what is the term "SIM" and what does it mean?
how much difference we have to provide when column steel staggered
can any body tell me that we stdy different grades of concrete $ their strength . as we knot the strength of conrete that this grade or ratio of concrete has this much strength ? even that we go for labortory test what is reason behind that?
how to calculate the runner (2*3) qty in cft. the length is 8 feet.
6 Answers CCCL, Gammon, Greenko, L&T,
Allowable wastage for ready mix concrete?
writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order
how much steel required for 1 sq.m area?
24 Answers AA Architects, L&T,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)