how we can estimate the M50 concrete for foundation?..

Answer / veer singh

you asked prepared A Estimate M-50 Concrete of foundation
First So, Depend A estimate at site because your site required is M-50 concrete So, it is justified the site is very critcal.
this is a Detail of estimate

S.no. description no. no. length width hieght Qty. unit
1 E/WinExcavation (As per site required)
2 E/W in surface (As per site required)
3 P/L Concrete M-10 (As per site required)
4 P/L Concrete M-50 (As per site required)
May be or may be not
5 Steel (As per site required)

Is This Answer Correct ?    0 Yes 0 No

how we can estimate the M50 concrete for foundation?..

Answer / satya

quantity comes in cum,i.e length x width x depth.its depend up on shape of foundation.

Is This Answer Correct ?    0 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

roll of DLC in road constructions

0 Answers  


how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.

0 Answers  


I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

0 Answers  


plz tell me the most used units and their conversion in civil engg?

1 Answers   L&T,


What is the roll of face bars in beams

1 Answers  






what is the difference between ribbed steel & tor Steel ?

1 Answers  


factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard

0 Answers  


What is componsation

0 Answers   Nagarjuna Construction,


How much depth of excavation have to do for Highrised builldings?if Raft foundation how much,and Pile foundation how much?

1 Answers   GMR,


how to calculate the dome surface area

2 Answers  


19. Are you a team player?

3 Answers  


sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience

0 Answers   L&T, Rail Vikas Nigam Limited RVNL, RRB,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16636)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)