A super elevation of 60 cm has been provided on a 8m wide road and a curve of 260m radius .calculate the max.speed in km/hr of the vehicle that can be negotiated safely? Plz answer with full solution.thanx
Answer / Suresh Kumar
To calculate the maximum safe speed for negotiation of a curved road with super-elevation, we use the formula: v_max = √[(R * g) / (b + esin(α))], where R is the radius of the curve, g is the acceleration due to gravity (9.81 m/s²), b is the breadth of the road, and esin(α) is the product of super-elevation height and sine of angle α (which can be calculated from the vertical curvature of the road). In this case: R = 260m, b = 8m, esin(α) = 60cm * sin(γ), where γ is the angle of super-elevation (as the value for super-elevation in centimeters was given, we assume a vertical curvature and calculate the angle γ using the formula: γ = asin((es / R)). However, without knowing the value of es (vertical curvature), I can't provide a numerical answer. Nevertheless, the procedure to find the maximum safe speed is explained above.
| Is This Answer Correct ? | 0 Yes | 0 No |
what is the lap length on column? state the farmula plz with explaination.
how to calculate the density of cement and how can we convert no. of Kgs of cement to Metric tonnes??
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
In case of concrete cube test were all three molds are attached together do you cast your cubes simultaneously at the three molds every 50 mm or one after the other?
why do you desire to change from your current position?
Density of 10 mm aggrigates
4 Answers BRB Construction, GPL,
How much kg of sand,cement will be for 1 sqmt(Blockwork-size 400x200x200)1:4 ratio & same for plaster
what are the layers of the national and heir aprox thickness??
Strength of brick?
How to design a beam without any typical(tuff) calculation. Answer Only by using site practical knowledge?
what is called camber in the road ?
I want to construct 1850 square ft of rcc apartment , with stilth parking , the site requires 18 ft of pile foundation , the apartment will be above ground parking , can some one guide me about the cost of construction of such structure in Pune ?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)