what are some possible sources of error in the CBR test?
Answer / tsholofelo
Some possible sources of errors in the California Bearing
Ratio (CBR) test are worn test tools, trash in the test
area, recent rain, old stream bed, missing the standard
height during compaction, compacting slower or faster than
compaction rate, and hitting the mould against hard objects
in order to remove the contents after compaction can remove
it from calibration.
| Is This Answer Correct ? | 6 Yes | 11 No |
M.C.Q
3 Answers Mitsui OSK Lines, TechInfini,
What is the standard size of a brick used in North India?
How much cement will require for 1Rmt Skirting laying
16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.
what is PEB structure
what is the use of dowels rod..?
10. Do you remain in good relationship with your previous employer / company where you no longer work /?
which chemical is used for corroded steel
What are the uses of layer?
how calculate the cube strength in percentage
what is the proportion of stones and concrete inplum concrete??
1.0 what is the permissible westage of steel in structural steel fabrication say gantry , trustle of power plant unit 2.0 what is the permissible westage of cement in construction work as above
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)