Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to estimate the earthwork,earth-filling for an isolated
foundation

Answer Posted / ramcharan

Earth quantity = aria isolated footing + working margin
Earth filling quantity = earth quantity _ isolated footing

Is This Answer Correct ?    4 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.

2031


What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?

2842


what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?

2255


How to activate isometric axes in cad?

1200


How to estabilish reinforcement Steel rolling margin for a building projects ?

4157


Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....

2394


how much shouid be the rate for ready mix concrete per cubic meter

2009


WHAT THREE SPECFIC JOB POSITIONS TO YOU TARGET FROM THE COMPANY?

2026


manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.

1750


I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com

2334


how we can find sieve #4 is 4.75mm?

2310


Form where IS456 is adopted in 1978?

1973


what is the function of GSB all class ?

1210


In cement concrete how to check a quality of material also proportion of material at site ?

1847


How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097

2237