How to replace dia of bar in beam like 25mm 3no.S at bottom But due to some reason on site 25mm bar is not available Then is it ok to provide 20mm 4no.S? Give description or Formula to calculate area of steel and replacement?
3 15643what are the tests conducted on cement,aggregate and concrete?briefly explain that tests procedure and limits adopted for safety side.
1 8430how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
1205How we can calaculate materials required for block work(1m3) block size 33cm x 20 cm x 17 cm, mortar 1:6
3 6223how we can calaculate cutting lengh for stiruups 6mm dia . column size 20 cm x 30 cm, cover 20mm
8 7095(Project Management Topic) What are the important criteria in the successful realization of the project?
1184Post New Civil Engineering Questions
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
what's the formula for calculate pcc for matt(45mm aggregate)?
Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?
How much the quantity of Dry material of Crush for 1:2:4 Concrete, using pan 3/8'' down....
How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.
how to find the cement bags and sand requirements for the one square meter of internal,external,ceiling plastering by using the various ratios like 1:3,1:4,1:5,1:6
if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?
Who built the sears tower?
Why you are leaving present job?
Define line type?
if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
What are the phases inspections are done by local authority while construction?
What is the difference between Fe 500, Fe 500 D and Fe 515.
Draw the cross section of a boundary wall and label its part with detailing?