why we are using MARSHALLING PANEL? what is the role?..

Answer / maulik vyas

marshalling panels are used as interface between field
junction box & dcs control panel..

It also isolates the dcs panel from feild control panel..

Is This Answer Correct ?    133 Yes 9 No

why we are using MARSHALLING PANEL? what is the role?..

Answer / kkrameshkumar

Marshalling means grouping of I/Os. Marshalling panel is
placed between the DCS system panel and field instruments.
In marshalling panel grouping of I/Os like Analog Input,
Analog Output, Digital Input, Digital Output and Pulse I/O
are done.From marshalling panel the I/O signals are
communicated to the system CPU/Controllers through
Isolation/Signal conditioners.

In marshalling panel we can easily identify the Input or
Output and easy diagnosis can be done in case of fault
finding.

Is This Answer Correct ?    97 Yes 6 No

why we are using MARSHALLING PANEL? what is the role?..

Answer / rajkumar

in addition to maulik points
3. marshalling cabinets location-- if located exactly will
save much cable cost and easy for maintenance people to
trace out cable routing and fault finding

Is This Answer Correct ?    53 Yes 10 No

why we are using MARSHALLING PANEL? what is the role?..

Answer / muhammad fawad azim

FUNCTIONS:
Signal conditioning, termination, signal isolation, cold
junction compensation, field device power supplies.

Is This Answer Correct ?    15 Yes 8 No

why we are using MARSHALLING PANEL? what is the role?..

Answer / rodney

There is a more practical reason for using a Marshalling Panel which becomes apparent if we imagine a multi-cable coming from the field and being connected directly to the I/O cards of a DCS. Whenever some kind of maintenance/test/check has to be performed just imagine the risk of interfering directly at an I/O card just to open some loop circuit. There would be the risk of touching another entry , loosing some bolt, and many other situations that could jeopardize the whole I/O card for some lack of other space specifically created to allow the proper access for maintenance and testing - the Marshalling Panel. Once the connections between all the I/O cards and a Marshalling Panel are done, tested and identified, no one wil have to deal with the I/O panel again, which means less risk and a proper place to do maintenance and testing, for there will be proper open/close connectors, fuses, isolators and all that the Project specifies.

Is This Answer Correct ?    8 Yes 1 No

Post New Answer

More Instrumentation Interview Questions

What is NODE in DCS?

2 Answers  


What is the reverse action and direct action

2 Answers   Samsung,


we have LPG spherical Tank and we want to install DP Xmtr for level measurement.below are the physical measurements Total height of tank is 1850 mtr but 0% level is 1000mm above bottom and 100% level is 450 below upper side.What is the LRV and URV and please mention the formula .The SG of LPG is 0.53 and Wet Leg method will be used.

7 Answers  


What is the formula to convert mv to temperature in k type thermocouple?pls simply elaborate? I got one ans.it is Temp=mv×25°+atmospheric temp,but here what is 25°,i confusef ,so pls????

2 Answers   HPCL,


how to work static pressure sensore how to work dpt

0 Answers  






How can I zero check of wet leg type DP Tx ?

6 Answers   ONGC,


What is the difference between local indicator(flow) and flow indicator?

2 Answers  


In control valve there are two type of valve seat we can use metal to metal seat & soft seat.On this valve seat i have following doubt. 1)I have never seen practically the internal assembly of valve so my doubt is that basically weather the seat is soft seat or metal its basic MOC is same as valve body(SS or CS) only in soft seat we are using PTFE ring & place on valve seat & in metal this PTFE ring is not threr am i correct??????? 2)what are the common general rule for using metal to metal seat & soft seat,means its depend on process parameter like liquid,gas, steam & on valve leakage class.

1 Answers  


What is 3 element control system

0 Answers  


HELLO FRIENDS plz tell me which are the PROTOCOLS we are using in PLC

3 Answers  


what deference between panel earth and systemearth

0 Answers   Tecnimont,


What is surge in compressors? How to detect and control it?

1 Answers   DEWA,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)