whats diffeence between dcs & scada operation.
Answers were Sorted based on User's Feedback
Answer / ankit
by dcs u control all parameter of the field on distributed
level and scada means it supervise and control the whole
plant parameter on central level.the dcs and scada full
name given states
dcs : distributed control system
scada : supervisory control and data acquisition
Is This Answer Correct ? | 29 Yes | 4 No |
Answer / nagarajan singapore
DCS is nothing but distributed control system which is
controlling all parameter by distributing data to separate
unit from the master data base along with the field
bus .this is indeppedent control system.
SCADA is supervisory control and data acquistion system
which is monitor based control from plc i/o .this one
deppendent control control system by controlling a limited
control
Is This Answer Correct ? | 17 Yes | 0 No |
Answer / likhit
The goals of DCS and SCADA are quite different. It is possible for a single system to be capable of performing both DCS and SCADA functions, but few have been designed with this in mind, and therefore they usually fall short somewhere. It has become common for DCS vendors to think they can do SCADA because the system specifications seem so similar, but a few requirements paragraphs about data availability and update processing separates a viable SCADA system from one that would work OK if it weren't for the real world getting in the way.
DCS is process oriented: it looks at the controlled process (the chemical plant or whatever) as the centre of the universe, and it presents data to operators as part of its job. SCADA is data-gathering oriented: the control centre and operators are the centre of its universe. The remote equipment is merely there to collect the data--though it may also do some very complex process control!
A DCS operator station is normally intimately connected with its I/O (through local wiring, FieldBus, networks, etc.). When the DCS operator wants to see information he usually makes a request directly to the field I/O and gets a response. Field events can directly interrupt the system and advise the operator.
SCADA must operate reasonably when field communications have failed. The 'quality' of the data shown to the operator is an important facet of SCADA system operation. SCADA systems often provide special 'event' processing mechanisms to handle conditions that occur between data acquisition periods.
There are many other differences, but they tend to involve a lot of detail. The underlying points are:
SCADA needs to get secure data and control over a potentially slow, unreliable communications medium, and needs to maintain a database of 'last known good values' for prompt operator display. It frequently needs to do event processing and data quality validation. Redundancy is usually handled in a distributed manner.
DCS is always connected to its data source, so it does not need to maintain a database of 'current values'. Redundancy is usually handled by parallel equipment, not by diffusion of information around a distributed database.
These underlying differences prompt a series of design decisions that require a great deal more complexity in a SCADA system database and data-gathering system than is usually found in DCS. DCS systems typically have correspondingly more complexity in their process-control functionality.
The company I work for has both DCS and SCADA products. The operator stations for each product line can use the same UNIX workstations. The systems share data (and thus form a composite SCADA/DCS system), but the SCADA database architecture is significantly different from the DCS data architecture, to the extent that the SCADA master station database looks to the DCS operators very much like some directly-connected DCS I/O. The DCS people are (of course) keen to simplify this to cut costs. However, they do not yet have a viable alternative for the mechanisms required in SCADA systems to have communications redundancy and data redundancy to provide the sort of SCADA system reliability that our customers expect.
If you look at most customer's system requirements specifications, a careful analysis of the data collection and data quality requirements will indicate if SCADA-style or DCS-style systems are appropriate. In general: the more features a system provides the more it will cost, so if you do not need SCADA-type data gathering facilities it will usually be more economical to use a DCS-type system. If you do need these facilities, you will pay for them.
The short answer: DCS and SCADA are still different things, it depends what the customer specifies as to which is appropriate for a particular installation.
I hope this has clarified more than it has confused. Also, it is my opinion based on my own experiences with DCS and SCADA. Others may have experience with systems that are designed to provide full SCADA and full DCS functionality in the one system.
Is This Answer Correct ? | 5 Yes | 0 No |
how many types of preheaters are in cement industry & what r they can any body explain?
why k factor is important to know in flow transmitter. if we don,t know k factor what will be issue we can face .
1 Answers Flour Tech Engineers (P) Ltd,
can anyone can let me know in Eurotron Micro cal 2+ calibrator in milli amps source mode we are not able to get 20 milli amps output it only produces 1.52 milli amps out, but display shows increase in milli amps , and err6 displays, let me know how to remove the err 6.
what is the daily job of an instrument commissioning supervisor
why bevelling is done in an orifice ?
what is function of ESD , and how is it work, explain with difination
1 Answers Bapco Bahrain Petroleum Company, BMB,
What is standard of DCS panel design?and what is step of DCS panel design?wiring and type of connector(screw or DB connector)
micromotion flow meter used for
I faced several time siemens ps2 positioner automatically getting Chang in it's set point direction after auto calibration So is there any causes biside this or any permissives ?
what is the diffrence between LCN and UCN
Which instrument used to calibrate the pressure switch?
What are the cable come out from the paddle type flow sensor.and how is further connections