my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..
Answers were Sorted based on User's Feedback
Answer / kavan patel
Step 1: Create REM Profile using SPRO (TC: OSPT)
SPROàProductionàRep ManufacturingàControl Dataà Create REM
Profile Using Wizard.
Save the profile and exit from SPRO.
1. Create Material Master with Fert and ROH as usual.
2. Create BOM as Usual.
3. Create Production Line with Capacity Category as :
0007 (i.e normal work center)
4. Create Rate Routing for Fert Material using TC:
CA21
5. Go to Change Material Master (Fert Material ) and
Attach REM Profile, Mark tick indicator for REM
Manufacturing. In MRP-4 View.
6. Create Production Version for this Fert material.
Select BOM, Select Rate Routing with No.
Step No: 2
Create Independent Requirements TC: MD61
Step No:3
Run MRP TC: MD02
Step No: 4
Go to Planning Table TC: MF50 and assign the quantities to
production line.
Step No: 5
Run Schedule Quantities are assigned and go to MD04 all
planned order are converted to RS Qty.
Step No 6:
Create Product Cost Collector for Fert Material: TC: KKF6N
Step 7:
Do the Back flush Using TC: MFBF
Enter and save the file….
Is This Answer Correct ? | 18 Yes | 1 No |
Answer / manuel
This is a very large question, but I tried to resume it:
We supose you have the rest of Master data created (Work
Center, Bill of Material, Routing ) , so I will only
explain the differences;
1.- Material Master: You have to create Product Versions
(C221), add this information with MM02 to materials.
Also you have to Fill View MRP4.
2.- It's neccesary a Cost collector.
This a very
Is This Answer Correct ? | 9 Yes | 4 No |
Answer / sundhu
Hi,
To customize this first need to maintain the Master data,
1) Material Master-> MRP4-> create & add Producion version,
2) Define the BOM-> CS01.
3) Create a Rate Routing->CA21.
And in Transaction data,
1) Create a Planned independent Requirements->MD61,
2) Run MRP->MD02,
3) Review the capacity through Planning Table->MF50,
4) Finally can create the Product Cost Collector->KKF6N.
Note:
KKF6N is a integration between PP & FICO.
Is This Answer Correct ? | 7 Yes | 2 No |
Answer / jinchandra
First of all make PP master data,before that create your
orgnisation structure,
After that go as bellow,
In material master view SELECT REM ALLOWED,
IN CUSTOMIZING [OPP3] SELECT THE REM PROFILE,
AGAIN IN MRP4 VIEW CREAT PRODUCTION VERSION BY USING TRSN
CODE C221.
CARRY OUT BATCH MANAGEMENT ,BATCH ASSIGNMENT, PP-PI SHEET,
MASTER RECEIPE,
go for product cost collector KKF6N,
Is This Answer Correct ? | 5 Yes | 4 No |
Answer / shamshuddin
Repetitive manufacturing is selected in MRP4 TAB
one is check box repetitive , REM profile , production
version (Each pcc create one PV).
month end process
1) std cost ck11n
2) mark and release ck24 other wise run Ck40n
cost center level
assessment and distribution
actual activity price calculation
revaluation of activities
actual OH calculation
wip
variance
settlement
Is This Answer Correct ? | 1 Yes | 1 No |
How does sap know that an operation has components as indicated by the component allocation indicator?
What is golive actually? What is the role of a functional consultant in golive actually?
how to create report in sap pp
What are some important tables used in pp (production planning)?
In SAP PP,how do you have relation with end users?
Integration between PP and SD module.
1.what are all the types in backflashing? and T-cde for it 2.what are the different places we can give back flush indicator? 3.what is product cost collector & its t-code? 4.what are all the costs involved in product cost collector 5.how many types of SOP?what is t-code for SOP 6.scheduling parameters for a production orders 7.how do you carry out capacity leveling 8.can you dispatch capacity for a single work center
What is finite scheduling?
What is meaning of customized reports?
Difference between Routing, Ref op set, Rate routing and Ref rate routing.
What is the use of sap material view and list out other parameters where sap material view is applicable?
In sap-pp what are the costing parameters?