my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..

Answer Posted / sundhu

Hi,
To customize this first need to maintain the Master data,
1) Material Master-> MRP4-> create & add Producion version,
2) Define the BOM-> CS01.
3) Create a Rate Routing->CA21.
And in Transaction data,
1) Create a Planned independent Requirements->MD61,
2) Run MRP->MD02,
3) Review the capacity through Planning Table->MF50,
4) Finally can create the Product Cost Collector->KKF6N.
Note:
KKF6N is a integration between PP & FICO.

Is This Answer Correct ?    7 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How does sap know that an operation has components as indicated by the component allocation indicator?

554


What is Phantom Assembly?

1081


Explain what is prt (production resource tools) in sap pp?

601


What is plm (product lifecycle management) in sap pp?

595


What is MRP Area or How can I excluede one storage location stock from MRP?

1328






What is the SPRO Path for requirement class and req. type?

3548


Can we use the same routine for materials undergoing the same process/operations? Can we avoid separate routing for each and every material produced?

601


Splitting of production order & product version

1334


Explain the planning steps for 100 products?

640


Difference between plan cost, Actual cost and target cost.

2615


What is routing in sap pp?

775


What are the reports generated in product cost controlling information system?

634


What is the use of t-code cs20 in bom?

700


What is SOP and types of SOP?

1257


Have you used Pull list or back flushing in REM?

1577