my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..
Answer Posted / sundhu
Hi,
To customize this first need to maintain the Master data,
1) Material Master-> MRP4-> create & add Producion version,
2) Define the BOM-> CS01.
3) Create a Rate Routing->CA21.
And in Transaction data,
1) Create a Planned independent Requirements->MD61,
2) Run MRP->MD02,
3) Review the capacity through Planning Table->MF50,
4) Finally can create the Product Cost Collector->KKF6N.
Note:
KKF6N is a integration between PP & FICO.
Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
How does sap know that an operation has components as indicated by the component allocation indicator?
What is Phantom Assembly?
Explain what is prt (production resource tools) in sap pp?
What is plm (product lifecycle management) in sap pp?
What is MRP Area or How can I excluede one storage location stock from MRP?
What is the SPRO Path for requirement class and req. type?
Can we use the same routine for materials undergoing the same process/operations? Can we avoid separate routing for each and every material produced?
Splitting of production order & product version
Explain the planning steps for 100 products?
Difference between plan cost, Actual cost and target cost.
What is routing in sap pp?
What are the reports generated in product cost controlling information system?
What is the use of t-code cs20 in bom?
What is SOP and types of SOP?
Have you used Pull list or back flushing in REM?