my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..
Answer Posted / jinchandra
First of all make PP master data,before that create your
orgnisation structure,
After that go as bellow,
In material master view SELECT REM ALLOWED,
IN CUSTOMIZING [OPP3] SELECT THE REM PROFILE,
AGAIN IN MRP4 VIEW CREAT PRODUCTION VERSION BY USING TRSN
CODE C221.
CARRY OUT BATCH MANAGEMENT ,BATCH ASSIGNMENT, PP-PI SHEET,
MASTER RECEIPE,
go for product cost collector KKF6N,
Is This Answer Correct ? | 5 Yes | 4 No |
Post New Answer View All Answers
Can anybody explain to me why the work scheduling view is required for semi-finished and finished products?
Why is work scheduling required for semi finished and finished products?
Mention what is the difference between stock transport order and stock transfer order?
How can you get planned orders scheduled so that you can do capacity leveling ?
Why work scheduling view is required for semi-finished and finished products?
What is serial number and where you will be configure
What are all the settings done for configuring the integration of pp with fico?
What is process keys
How do I default it 41?
Splitting of production order & product version
What are the customer activities followed for pp module ?
Explain what is the meaning of exploding a bom?
What is Material status and which view of the material master it is available?
What is the difference between “planned consumption” and “unplanned consumption”? Can safety stock calculation be done on either of these?
Control keys