Answer / amit
it depends upon dia of bars...for example HYSD Bars as per IS 2502
Dia of bar Hook's length
upto 8mm 90mm
10mm 110mm
12mm 130mm
16mm 175mm
20mm 225mm
25mm 275mm
32mm 350mm
Is This Answer Correct ? | 7 Yes | 2 No |
Answer / mukhram singh
it depends upon dia of bars...for Hook's length both side
2*10*dia.
Is This Answer Correct ? | 4 Yes | 0 No |
which is cost effective Steel Structural or Concrete Structure building?
I just got a first job in Maharashtra and m a fresher. My task is estimate the cost of excavation of earth with J.C.B. can anyone tell me how to do this??
Q1) I am having an interview in a construction company for a large sewage project . Since I have not done any such project , there are some queries from my end. Pls. help me to solve them. I will be thankful to you :- a) Normally for large project 400-600 houses & around 1600 peoples , how much dia pipe is used and which type of pipe is used? b) For trenching , I have heard that IS 1200 implies, what are the rules of calculating earthwork in case of depth of 2m or above ? c) To prevent soil to fall when depth of trench is more , what steps are taken and how there qty. is calculated . Like I have heard about timbering . what is this ? d) What are the rules for disposing off the excavated soil ? e) How the pipes that are used are being jointed? f) In case of cleaning on choks , is there any intermediate things provided? g) For foul gases any outlets are provided thru out length of pipeline? h) What is the flow digram like from houses thru small pipe to main pipeline than where main pipeline disposes wastage ? i) Any other thing that has to be kept in mind while calculating earth work for excavation like steps are made and other things? How earthwork is calculated in case of steps ? Pls. explain with a sketch. Regards,
practically where this hinge and roller condition used
What is meant by solid geometry?
suppose that 156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.
what is pH value of sewage&water.if pH value is given then how to calculate H+.
can u use instead of water milk for concreting
Highest compressive strength of M15 concrete that can be gained at 28 days
1) One mason per day how many cu.m work will do as per list given a) Brick work,hollow brick work and cc block work and plastering how many m2 per day 2) one carpenter per day how many m2 will do as well as scaffolding how many m3
12 Answers Al-Futtaim, Arihant, GS, Gulf, L&T, NCC, Paras Buildtech, PR Constructions, Ramco,
How much actual % of wastage of steel.
how to know rcc strength