how to calculate sand, aggregate and cement in m25 concrete?
Answers were Sorted based on User's Feedback
Answer / rohit singh
Grade m25= 1:1:2 , sum=1+1+2=4
Dry concretein 1 cum =1. 52
Cement =1. 52/4=. 38*28. 8=10. 94bags cement /cum concrete
Sand=1. 54*1/4=. 38cum
Aggregate=1. 54*2/4=. 76cum
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / narayan rijal
1.52/(1+1+2)*28.81=cement bags
0.41=sand
0.83+aggregate
Is This Answer Correct ? | 3 Yes | 8 No |
What is capicity of cap lock scffolding stander(vertical member) and ledger of different size?
sir i have 2700sq.ft area.i wish to make a coomercial space including this area.sir what could be the estimated cost of 3 story bulding in varanasi.
What is OSHA compliance?
What Should be the CBR Value for Transported (Selected) Soil.whether it can be 5% or not ?
What is the acceptable percentage of slump in Mix concrete?
what are the code used for residental building?
How to calculate the sand and aggregate in concrete
what is the criteria for placing reinforcement in footing and slabs e.g which span have to place first.
4 Answers Al Futtaim Carillion, NTPC,
What is meant by M20 grade of concrete???
Which type of question ask for written test for civil diploma trainee
1. why more stirrups are provided near the support? 2.where more stirrups is provided in a column and why? 3.why extra bars are provided at the top of beam? 4.what is the difference between overlap and lap lenght? 5.what is development lenght
How to take cutting length of Stirrups when 10 leg has given Size is 1200x1200