how to calculate sand, aggregate and cement in m25 concrete?

Answer Posted / rohit singh

Grade m25= 1:1:2 , sum=1+1+2=4
Dry concretein 1 cum =1. 52
Cement =1. 52/4=. 38*28. 8=10. 94bags cement /cum concrete
Sand=1. 54*1/4=. 38cum
Aggregate=1. 54*2/4=. 76cum

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day

1582


How much cement,sand,bricks and water needed for 1square metre brick work?

1336


What is the largest concrete dam in the world?

686


List out some of the checking’s, done at the completion of construction?

703


What is meaning of FREE STANDING STAIRCASE ?

2485






Draw the cross section of a boundary wall and label its part with detailing?

4148


Why are the bolts that hold steel rails together in oval holes?

699


what is right & short method of measurement of slab&beam

1640


how to caliculate required amount of cement and sand required for 1cu.m.

1737


Which percentage of carpet area use in plot area of office building.

1390


what would be the design load of R.C.C Cooling tower per cell.?

1559


How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?

1873


how to calculate load bearing column

3053


sir, please send me the web address of chennai railway to know the online examresults of junior engineer[civil].

1679


Define What are the reasons for geotechnical site investigations in Uganda?

686