how to calclate the cemment for 1 cubic metre of 1:2:4 concrete
Answers were Sorted based on User's Feedback
Answer / dipak rakibe
TO DERIVE THE QUANTITY OF INGREADIENT MATERIAL FOR 1 CUBIC METER OF CONCRETE FOR M-15 GRADE
Proportion for M-15 Concrete is 1:2:4
For Easy Calculations Take/Assume 10 Cu. m. of concrete.
Proportion
10 X 1.52 = 15.2
(Here 1.52 is the dry volume factor)
A) Quantity of Cement =
For 10 cum of concrete
(1/ 1+2+4)= 0.143 X 15.2 = 2.17 Cum
1 Bag of Cement = 35 Liters = 0.035
Quantity of Cement Bags = 2.17/.035 = 62.10 Bags
for 1 cum of concrete = 6.21 Bags
B) Quantity of Fine Aggregates/Sand
For 10 cum of concrete
(2/ 1+2+4)=0.285 X 15.2=4.33 Cum
Quantity of Sand = 4.33 Cum
for 1 cum of concrete = 0.43 Cum
C) Quantity of Coarse Aggregates/ Gitti
For 10 cum of concrete
(4/ 1+2+4)= 0.571 X 15.2 = 8.68 Cum
Quantity of Gitti = 8.68 Cum
for 1 cum of concrete = 0.87 Cum
Summary =
A) Cement Bags= 6.210 Bags
B) Fine Agg./Sand=0.43 Cum
C) Coarse Agg./Gitti = 0.87 Cum
BY Dipak Rakibe
Is This Answer Correct ? | 9 Yes | 1 No |
1 cum of 1:1:4 concrete
Dry volume equal is 1.52
Cement equal is 1/6*28.8*1.52 =7.2 bags cements
= 364.8 kg cements
Is This Answer Correct ? | 0 Yes | 3 No |
What is the Maximum & Minimum size of rod using on the column?
What is a BBS?Find out the cutting length for a foundation size 600 x 600, cover 50 mm?
in construction feild make the column rods are uneven ( e.g 1 column we have 6 nos of bars that 6 nos of bars are varrious level- 1 bar 10';2 bars 9';3 bars 8') what is resion to put different level if difference are required or not?
what is the proportion of m20 grde concrete? also how much water is required for this proportions? As there were any formula for water-quantity?
How to calculate soil bearing capacity of soil?
how to calculate the quantity of cement,sand and aggregate when the ratio of mixing is 1:2:3
0 Answers Ajnara Group, Assosa University,
How many square meter can a worker/labor demolish a structure per day?
the coefficient of curvature for a well graded soil must be inthe guage 0.5-1 3-4 4-5 none
wht is off shore structure
How to calculate brick work quantity?? Block work quantity??
why did you choose this career
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?