Answer / deepak katyal
Construction joints have been provided at 1/3 point of span
on the basis that moment is least there.
Is This Answer Correct ? | 20 Yes | 2 No |
What is mean by uniaxial bending
how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building?
how to convert feet value in meter value?
How much depth of excavation have to do for Highrised builldings?if Raft foundation how much,and Pile foundation how much?
Why are L-beams (cast monoloithic with slab)that usually occur at the slab edge, provided with overhangs?
What is the Density of Steel & Conccrete
How much quantity of cement Bag for block masonry (1:4) for 1 cu.m? Block size (150x200x400) Mortar Thickness 20mm
I want to join bhel because
Water absorption for stone?
What is the snap size in civil and how can we create it?
Cemen-1 Fine agr.-2 Core agr.-3 calculate for per 100 qube feet (qubic feet wise)
how to find hardness of water?why it should be determined?