How many cement mortor dry quantity required for 1m3 ?(1:4)
Answers were Sorted based on User's Feedback
Answer / pavan
total quantity required would be 1.57 cum of dry mortar,
including 20% wastage.
Dry volume of mortar is 30% more than wet volume.
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / rehaan khan
For rcc work it will 1'57 cum
For brick masonary '30cum
For plaster work it will 1'60cum..
Is This Answer Correct ? | 0 Yes | 0 No |
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
The foundations are placed below ground level, to increase?
what is the difference between TOR & TMT
Quick setting cement's setting time?
7 Answers TNPSC Tamil Nadu Public Service Commission, UPPSC Uttar Pradesh Public Service Commission,
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
In which direction is bottom bar of rectangular footing is placed in short or long.
how to mack bbs
flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force
what"s the cement, sand, aggregate(consumption) quantity for 10 cm thick roof slab (1:2:4)
WHAT DLC DESIGN IN CONSTRUCTION
Respected Sir, I am from a hilly place called Darjeeling ,I have constructed house of 9 column out of which 4 of the column is under water , i have put rcc slab on top and on top of the rcc slab i have construced two room house with bricks and light roof , now i am planning to change the light roof with rcc slab for the two room, my main concern is will the column under water will hold the load of the new rcc slab coz it already 10 to 12 yrs old , i dont know what to do , can u advice me regarding this matter, weather to leave the upper floor roof light or make it rcc slab.(If i put the slab , it will require 45bags of cement and u calculate how much of steel and sand and pebbles) thanks with regard Anand
Define What does civil status mean?