why there is no
concrete mix of
ratio 1:.5:1
Answers were Sorted based on User's Feedback
if you calculate the quantity of cement in this ratio, it
is more than 450kg/m3( it is around 873kg/m3). as per IS
456, there is no effect of cement above 450 kg . there is
so many problem above 450kg/m3, due to heigh quantity of
cement heat of hydration effect is more. crecks problem
also occure. so we go for design mix.
Is This Answer Correct ? | 7 Yes | 0 No |
Answer / ashis malakar
because of with the proportion of mix concrete is not to be
useful in any kind of construction due to it's low
compressive and tensile strength and it's low durability
.
Is This Answer Correct ? | 5 Yes | 8 No |
In which grade of steel the laping length required is more,Fe 415 or Fe 500 ? and why?
what is the meaning of morth
How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site
A ground is nonengginered fill 15 years back; how we can find the level of consolidation and bearing capacity
how to calculate quantity of cement and sand for plastering works in CM 1:6 proportion.....plz answer anyone.....and write the formula...
What out turn civil works
What is the difference between nominal mix and design mix?
what is the service corridor?
what is the quantity of formwork in shuttering and barbending is done by 1 mason and 1 helper
List out the densities of different construction materials such as brick, steel, sand, aggregate etc...
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard
What is the bar bending schedule