What is the cement and sand consuption of 1:4 block work
Answers were Sorted based on User's Feedback
Answer / rakesh
cement part = 1/5, sand part = 4/5
now 1m3 of cement weighs 1440 kg and cube contains only 1/5part of it as cement. therefore, 1/5* 1440 kg cement present . and rest as sand..i.e. 1440*4/5kg
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / abdul rasheeth
cement &sand ratio is 1:4
i.e.,1 ratio cement for 4 ratio of sand
cement quantity for this ratio =ratio of cement/ratio of sand
=1/4=0.25 ratio cement
we know that 1 m^3 cement =1440 kg
therefore amount of cement =0.25*1440 = 360 kg/m^3
lly the amount of sand is =360*4 =1440 kg/m^3
Is This Answer Correct ? | 6 Yes | 4 No |
what is periode of deshuttering of slab our span length 21m,and width 2.5m grade of concrete M-35
19. Are you a team player?
Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.
fe415
what is curve ranging??
wat happens to the foundation when only live & dead loads are considered( wind load is excluded) during the design of tall structures. options are: a)only settlement in the internal structure and not external structure b)only settlement in the external structure and not internal structure c)no differential settlement d)none of the above
4 Answers BBJ Construction, IOCL,
How to preparation billing for high rise building? anyhow can give the tips
What is the basis of choice for cement sand plaster in ratio 1:4 and 1:6 on interior walls of a residential apartment.
What is the proportion of M 45 grade of concrete
flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force
what if i want to lap a 20mm dia and a 16mm dia together wat will be the lap length?? a) 1m b) 80mm
Technical Question of Civil Engineering
0 Answers DLF, Era Infra Engineering, L&T, Mrkr Constructions, NBCC,