What is the cement and sand consuption of 1:4 block work
Answer Posted / abdul rasheeth
cement &sand ratio is 1:4
i.e.,1 ratio cement for 4 ratio of sand
cement quantity for this ratio =ratio of cement/ratio of sand
=1/4=0.25 ratio cement
we know that 1 m^3 cement =1440 kg
therefore amount of cement =0.25*1440 = 360 kg/m^3
lly the amount of sand is =360*4 =1440 kg/m^3
| Is This Answer Correct ? | 6 Yes | 4 No |
Post New Answer View All Answers
why +1 to be followed for calculating the no of bars in BBS. Please explain
cement and sand required for one block of size 0.23*0.15*0.46
What are the responsibilities of a construction manager?
On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??
What are the disadvantages while using stone dust as filler in pavements?
Does VDF add strength to the flooring apart from preventing water ingress?
show answer/ calculate-1-2-4 ratio-concrete -cement-sand- metal-water - please brief calculation
Will going from a 3-tap to 6-tap increase water pressure?
What is thumb rule in quantity and cost estimation of a residential building?
What are some structures that may be subjected to fatigue?
what is diffrence between catchment area,watershed and basin?
What is Rankine Cycle?
What is pre-stressed concrete?
How do you compute volume of airflow?
detailed calculation of the amount of cement used?