1.how to calculate the nails qty in shuttering of column,beam, shear wall.
2.how control the binding wire wastage in building project.
3.
Answer / ratheesh
.750grms to 1Kg nails for 1sqm shuttering.
u can use single binding wires
Is This Answer Correct ? | 2 Yes | 2 No |
Why do we use steel in Column? Why HYSD bar is preferable than plain bar?
What is the density of steel? what is the IS code for steel structures? 1t/m2 = ?KN/m2 ??
how many no of solid blocks and bricks required for construction of wall for 100 sqft?
what is the water cement ratio for plastering
why seismic analysis not done during design of slabs
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?
what is the shuttering normal clear cover for footings, walls, beams & columnms
While casting slab at what length slab casting should be stop
i want measure water capacity in 25'diameter and 7'height of water in circular storage tank in liters how?
Clay and silt content in a good brick earth must be at least
what is the weight of sand,corrse aggregate and steel,for 1cum
1 Answers Gulf Asia, Jade Software, Sand,
what grade of concrete to be used for lintel when reinforced with bamboo in place of steel?????????