deshuttering time for RCC for DPC over the foundation.
Answers were Sorted based on User's Feedback
Answer / vignesh s
For beam and slab
side deshuttering-
1 Day, slab bottom-
10Days, beam
bottom- 14Days,
cantilever beam
bottom- 16 Days
above days will be
followed after
completing the rcc
slab.
Is This Answer Correct ? | 11 Yes | 0 No |
Answer / mani d.c.e
De shuttering Beam and Slab - 1day
Slab Bottom below 3m span-14 days
Above 3m Span 21days
Beam Bottom - below 3m span - 14dayss
Is This Answer Correct ? | 8 Yes | 1 No |
Answer / amit
for side shuttering=1 day
but as per is 456-2000,Bottom deshuttering of slab and beam are done when Concrete achieved 65% of its actual ulmimate strength.
Is This Answer Correct ? | 0 Yes | 2 No |
ground floor columns and beams are reinforced by 4 Num's 16MM @ Corners AND 2 Num's 10MM @ centre.... And the nxt top floor columns and beams were lapped by 8 num's 12MM dia bars..... IS THIS CORRECT ????
What is the accepted silt content in sand for concreting purpose by volume method?
how can change 10mm dia @275 c/c bar spacing to 12 mm
Why provide strripus in a column minimum and maximum spacing.
Define What is a projection line?
how much dry volume of cement in 1cum in m20 grade
what is silica fumes or micro silica? and whr is it used? wat r its advantages?
What do you mean by the word 'shear'?
what ratio of cement and sand we used for making cover
The Hinged and Roller support is same or differnt if it is differnt how does it differs
difference between specification and method of statement
How are freeway bridges built?