Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


How can decide the MVA rating of power transformer for
substation like 220/132, 132/66, 66/33kv etc or even higher
kv rating of substation????
Send me the strictly technical answer that shows your strong
technical aptitude.

Answers were Sorted based on User's Feedback



How can decide the MVA rating of power transformer for substation like 220/132, 132/66, 66/33kv etc..

Answer / siva

MVa Rating is Depends upon the Load when Load is
increased current will increase so we design for different
rates of Mva Depends upon the load

S= 1.732* V*I for Ex 50 MVA

50* 10^6 = 1.732* 220* 10 ^3*I To Calculate the I Value
is 131 in Hv side Lv side 218 A

Is This Answer Correct ?    23 Yes 4 No

How can decide the MVA rating of power transformer for substation like 220/132, 132/66, 66/33kv etc..

Answer / j.karthik

The MVA rating is only based upon the generating MW capacity
of the plant.
For Example:
50MW is generated in the Powerplant.(i.e. Generator
capacity is:50MW,11kV,0.8P.F,3000RPM)
Now we like to connect this 50MW power to the E.B.grid
then we use one Step UP Transformer i.e. to step up the
voltage from 11kV to 220kV.
Now we can calculate the MVA rating of that step up
transformer as:
i) MVA = MW/costeta
MVA = 50/0.8 = 62.5MVA.

This is the answer.....

By,
Karthik(Engineer)

Is This Answer Correct ?    11 Yes 7 No

How can decide the MVA rating of power transformer for substation like 220/132, 132/66, 66/33kv etc..

Answer / srikanth.kondru

very simple

we need to know the Load of the sub station ..
for example it is 1000 H.P
as we know that 1 H.P =1.5 amps
voltage is 220 KV
power ,p = 746KW = 1.732*0.8*220KV*I
I = 746 KW/1.732*0.8*220KV
= 2.4 amps
S=220*2.4*10^6 =532 MVA

Is This Answer Correct ?    5 Yes 3 No

How can decide the MVA rating of power transformer for substation like 220/132, 132/66, 66/33kv etc..

Answer / milinda4p

The MVA rating of a power transformer depends on the load
connected to the transformers. this can be calculated (for a
grid transformer) by calculating the total MVA of the
primary substation transformers connected to it.Generally
this is calculated with a extra space for load connection.

Is This Answer Correct ?    4 Yes 2 No

How can decide the MVA rating of power transformer for substation like 220/132, 132/66, 66/33kv etc..

Answer / k.prakashchandra

The present load and anticipated load growth in the coming
10 years.

Is This Answer Correct ?    3 Yes 3 No

How can decide the MVA rating of power transformer for substation like 220/132, 132/66, 66/33kv etc..

Answer / raju

transformer is working only based on load. frequency was not changing, so it is called mva

Is This Answer Correct ?    2 Yes 6 No

Post New Answer

More Electrical Engineering Interview Questions

What should be the voltage between neutral and earth of a UPS?

4 Answers  


Please tell me if you are electrical engineer,and you are appointed for the maintainance of Electrical Power plant,then which parts of the plant deal with you.Also tell how these parts/components work.

1 Answers  


what happen when we add mentos in cold drink?& why?

0 Answers  


Difference between KW & kVA

7 Answers  


How can we find out LT UG cable fault (size,from-4*25mm sqr to 4*300mm sqr)? How mani types UG cable faults?

0 Answers  


WHAT IS THE SPECIFICATIONS CONSIDERED DURING DESIGN FOR THE OVER CURRENT RELAY?

3 Answers  


how to find the transformer neutral copper earthing size 

1 Answers  


What are the Return ( Monthly / quarterly/ Annual submitted to Electical Inspector for an establishment (Factory in Maharashtra-- Small scale category having seperate HT line of 22KV ) as per Maharashtra Electricity Act

0 Answers  


what is surge impedance loading?

1 Answers  


Testing procedure of DG alternator stability test

0 Answers   Amprotec,


WHAT IS IEC? & WHAT IS BENEFIT TO PRODUCT FROM IEC?

0 Answers   BMC,


Explain the different regions in frequency response?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)