I need to plaster an area of 1500 square meter. how much
quantity of cement and sand need for this.?
Answers were Sorted based on User's Feedback
Answer / mohammed aijaz hussain
Let the thickness of plastering be 12 mm and CM(1:4)
Volume of wet mortar = 12 mm X 1500 sq.m.
= 18 cu.m.
Add 20% for depressions, joints and wastage
= 3.6 + 18 = 21.6 cu.m.
Volume of Dry Mortar = 1.3 X 21.6 = 28.08 cu.m.
Cement required = 1/5 X 28.08 = 5.62 cu.m.
= 160.6 Bags
Sand required = 4/5 X 28.08 = 22.46 cu.m
Is This Answer Correct ? | 49 Yes | 5 No |
Answer / ajith
For 1:6 plastering of 20mm thick cement needed is 150 bags or 7500kg n sand needed is 30cum.
Is This Answer Correct ? | 15 Yes | 10 No |
Answer / durgam
i need for 500sqm platering works ratio is 1:3 and how much required cement
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sandip santra
actually 410bags cement required in 12mmthk plaster in 1:4
ratio.
Is This Answer Correct ? | 1 Yes | 7 No |
Answer / ahmed
Cement-1mt2 @10mmthnk-15.62Kg required Ratio 1:4
Sand=1mt2 @ 10mm thnk- 62.5 kg required
u need-468.6 bags of cement
U need-1875 Bags of Sand
Is This Answer Correct ? | 4 Yes | 12 No |
what is preposition of M-5 grade
3 Answers Montag Infrastructure,
i just want to know how much require sand and cement for 1 sq.mt including wastage. Please guide me as soon as possible.
In block work seawalls what is the purpose of slip joints?
where you provide on column
what is Fe415 & Fe5oo? also what are types of steel?
How To do Steel Design of Beam,Columm,Slab,Staircase,Wall?
can we use .5 water-cement ratio for any type of cement?
Why do we use steel in Column? Why HYSD bar is preferable than plain bar?
Project at andheri west mumbai total area of 116000 sq ft near by..Please help me out for quotation plan is ready basic details are with me , please help me out .I will mail u in autocad also.
Please provide detail I.S standard code for using crush sand instead of river sand for plaster and concrete grade M15, M20, M25 and M30 and its mix design
Why are L-beams (cast monoloithic with slab)that usually occur at the slab edge, provided with overhangs?
what is the concrete mix design ratio of railway sleeper??????