Answer / r.k sharma


IS code 456-2000 states that Forms shall not be released until
the concrete has achieved a strength of at least twice the
stress to which the concrete may be subjected at the time of
removal of formwork (para 11.3).Minimum Period Before Striking
Vertical formwork to columns, walls, beams is 16-24 hours.
CC/RCC for DPC on plinth is never subject to any stress and
meant for retaining the material till Cement sets.As such it
should not be measured separately and treated as incidental to
the Work of DPC.

Is This Answer Correct ?    6 Yes 0 No

Should vertical shuttering done for CC/ RCC for Damp Proof Course (DPC) be measured? ..

Answer / anupom

Above answer is right, also
THe thickness of DPC is very less(apprx. 25mm) and is
generally applied as a coating layer for plinth level. Thus
the vertical shuttering may not be measured but this solely
depends on the contract specification.

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

What is the snap size in civil and how can we create it?

0 Answers   L&T,


what is mean by Face bar using in coloums?

1 Answers  


what is the detention period for oxidation ponds

2 Answers  


why you considers yourself suitable for the post of site engineer

5 Answers   Consultancy, Nalco, Ritspin Synthetics,


What is m20 and What is  20 ? 

2 Answers   Sukhwani Constructions,






What is made from large rocks, which protects the base of cliffs?

0 Answers  


Will going from a 3-tap to 6-tap increase water pressure?

0 Answers  


what is P.C.C ?

13 Answers   RCC,


1)What is the total volume of aggregates required for 1cu.mtr.solid hard concrete? 2)What is total mass of wet concrte and dry concrete after 28 days of M25? 3) Is 28 days strength is the final strength of concrete or it gets increasing as the time period increses.? 4)What is the volumetric proportion of concrete grade of M25.M30,M35,M40

0 Answers   AVS,


if size is 235cmsx15cmx100cms so how many cement bags and how many sand bags are used for concrete mix

0 Answers   Ras Engineering, UltraTech,


How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.

0 Answers  


What is .Dwg?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)