why efficiency of combine cycle power plant is more in winter then summer ?..

Answer / pal

efficiency of a rankine cycle can be increase with two ways.

1)increase the upper temparature
2)decrease the lower temparature.

Lot of experiment says the second way is the most effective way as ɳ=1-(T2/T1).
In winter the lower temp is low than in summer.
Thus the efficiency increases.

Is This Answer Correct ?    5 Yes 4 No

why efficiency of combine cycle power plant is more in winter then summer ?..

Answer / ns satyaraj

in rankine cycle lower temperature is of condenser which is constant in both seasons but question is for combine cycle where atmospherc air is compressed and heat is added in combustion chamber and gases are expanded in gas turbine. here since density of air is more in winter than in summer so compresser has to do less work so efficiency is more

Is This Answer Correct ?    0 Yes 0 No

why efficiency of combine cycle power plant is more in winter then summer ?..

Answer / sohail

in Rankine cycle , lower temperature is of condenser which
is constant in both seasons, then how efficiency increase ?
what effect on brayton cycle ?

Is This Answer Correct ?    0 Yes 1 No

Post New Answer

More Mechanical Engineering Interview Questions

Why large boilers are water tube type ?

0 Answers  


Dfine an ortographic drawing?

0 Answers  


what is milling and types of milling?what is drilling and types of drilling? what is tapering and their types?

0 Answers   IOCL, TVS,


What are the 3 parts in indicator diagram?

0 Answers   RRB,


with the aid of schematic and block diagram describe the control system involved in a student passing a control system engineering examination.use standard terminologies and specify all the system component involved.

0 Answers  






in engine when the engine stops are the pistons were stopped in between or they complete the process.

6 Answers   Honda,


Study the attached ACS 790 AHU and boiler GUI and refer to the video on the software usage, catalog and the step by step document (page 9) to perform the following task: List in a table form the controllers and all their connected I/O for the boiler and the AHU.

0 Answers  


what are the uses of eutectic alloys?

0 Answers  


Abrasion is a cause of the gear failure form

1 Answers  


distance between the power generation and the distribution to the application is fixed or vary

0 Answers  


what will be the change in weight ( mass ) of a person when us he is coming down / up in the elevator ?

2 Answers  


1 hp how much watt?

8 Answers   Blue Star, Toyo Engineering,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)