how to calculate cement mortor for wet and dry mix for
different ratios
1 cubic meter wet mix requried 1.54 cubic meter of dry mix.we
have to use the formula for finding cement,sand,jelly.
for finding cement 1.54 x c/c+s+j we can find the quntity of
cement for different types of ratios
Is This Answer Correct ? | 4 Yes | 1 No |
How many number of bricks required for 1 cum & how much mortar quantity require for 1 cum
22 Answers Assurance, Campus Interview, R Tech Developers, Ramdev Construction, Synergy,
What is diversion tunnel in a dam?
Explain the various stages of the project planning process in construction?
Explain what is Critical Path Method (C.P.M)?
Wat is meant by Aecron brick?
you are working as a QC in hihg rise building. when what"s ur responsibilities works?
What Reinforcements Are Used In The Process Of Prestressing?
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
0 Answers First American Corporation, GS Infra, L&T, Real Sociedad,
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building
cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com
How many kilograms of 12 mm coarse aggregate required in cufic feet for one cubic meter of M25 grade concrete
what are the five benefits of using standard terminology in the measurement process?