1:5:10

isme 1 kya h
5 kya h
10 kya h

Answers were Sorted based on User's Feedback



1:5:10 isme 1 kya h 5 kya h 10 kya h..

Answer / narendra

1 cement
5 sand
10 Aggregade

Is This Answer Correct ?    23 Yes 1 No

1:5:10 isme 1 kya h 5 kya h 10 kya h..

Answer / sainath

1 cement
5 fine aggregate
10 course aggregate

Is This Answer Correct ?    13 Yes 1 No

1:5:10 isme 1 kya h 5 kya h 10 kya h..

Answer / venkatesh

1 is cement
5 is sand(fine)
10 is aggregate(corse)

Is This Answer Correct ?    12 Yes 0 No

1:5:10 isme 1 kya h 5 kya h 10 kya h..

Answer / md gyasuddin ahsan

In P.C.C
1 is cement
5 is corse sand
10 is aggregate

Is This Answer Correct ?    2 Yes 0 No

1:5:10 isme 1 kya h 5 kya h 10 kya h..

Answer / shivam sharma

1 is cement
5 is sand(fine)
10 is aggregate(corse)

Is This Answer Correct ?    1 Yes 0 No

1:5:10 isme 1 kya h 5 kya h 10 kya h..

Answer / praveen kumar

1 cement
5 dust
10 rodi

Is This Answer Correct ?    0 Yes 7 No

1:5:10 isme 1 kya h 5 kya h 10 kya h..

Answer / mohit

1 cement
5 rodi
10 dust

Is This Answer Correct ?    2 Yes 12 No

Post New Answer

More Civil Engineering Interview Questions

what is rebaring?

2 Answers   SSC,


How you read 5x3x1 #4 @ 20" 0/C in steel structure?

0 Answers   Ansu Construction,


define the strength

0 Answers  


What is the Laplenth for Reinforcement for Verticl and horizontal Structures as per IS code?

4 Answers   DLF, L&T,


How much of the strength of concrete comes from post- production curing?

0 Answers   EE Limited, Focus, Lafarge,






How much Strength of the cube can attain in 7days comparative 28 days strength?(as per IS code) ( specify the ref.clause also)

8 Answers   CCCL, L&T,


What is the dimension of Slump cone which is used to measure the Slump value of concrete? Slump value for Pile concrete? Slab concrete? Column concrete?

3 Answers  


How Much the Lean concrete Density?

0 Answers   Techno Unique Infratech,


what is tension footing?

0 Answers   Wah Engineering College,


what is the criteria for the finalisation of pavement thickness in road project?

0 Answers  


binding wire requirement in rcc structures

6 Answers  


How to calculate numbers of carpenter, fitter, mason, unskilled worker on the basis of built up area or floor plat area of building?

2 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)