Answer / jr suthar
By calculating the total load of building and safe bearing
capacity of sub soil, We can find out that the sub soil is
capable to resist the load of 5 story building.
Is This Answer Correct ? | 48 Yes | 1 No |
Answer / p.govindarasu
i calculate the ground resisted for a five floor building
with of help of safe bearing capacity of soil
Is This Answer Correct ? | 24 Yes | 2 No |
Answer / samsul
by calculating the total superstructure load of the building
and the safe bearing capacity of the soil where the
foundation is laid down.more precisely adding (the column
weight - weight of the soil of column volume)
Is This Answer Correct ? | 1 Yes | 0 No |
What are the Noms/8hr for Concrete Work for Mason,Carpenter,Steel Fixer
How much does it cost for a R.C.C roof slab of size (25 X 20) given in feets using 1:2:4 concrete mix of M20?
Different sizes of Hollow blocks and its weight. Thanks.
What is the actual formula to calculate dry consumption of 1cubic meter m20 Concrete???? Plzz tell seniors it is urgent..
What is the mix proportion of m30 grade?
how to calculate number of bricks
In case of tunnels (Railway) what is the way of securing a wall beam?
For 25mm thick plastering how much sand and cement is used for 1 sft
1 Answers Assurance, Design Consortium,
What are Standard weights for concete of gradeM10,M15,M20,M25,M30 Etc.
What is the quantit;(pratical method) of cement, sand, and gravel to be used in M25 grade of concrete for 1000 x 1000 x 1000 mm of sand (for cement please mention in kilos, and for sand and gravel please mention in cuft
What is difference between load bearing structure and frame bearing structure ?
2 Answers Sathiapal Engineers,
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???