in our transmisison sub station why we step down firstly
132kv\33kv then 33kv to 11kv. can we direct step down 132kv
to 11kv.
Answers were Sorted based on User's Feedback
Answer / gudsam
WE USUALLY FOLLOW THE SYSTEM OF TRANSMISSION OF TWO TYPES.
FIRST, WE STEP DOWN HIGHER VOLTAGES TO SLIGHTLY LOWER ONE TO
DISTRIBUTE SOME INDUSTRIES OR BIG CONSUMERS INCLUDING THE
LINE LOSSES. THEN WE USE THEM TO TRANS MITE TO DOMESTIC
PURPOSE. SO THEY KEEP THEIR VOLTAGE LEVEL HIGHER AS THERE IS
A HUGH AMOUNT OF LINE LOSSES IN THE TRANSMISSION LINE.
THAT'S WHY THEY SET DOWN FIRST AND THEN TO LOWER ONE.
| Is This Answer Correct ? | 9 Yes | 2 No |
Answer / sudhir a kadam
usually this is done looking into the practical
requirements and availability of the transmission line. It
is not at all necessary that the HV 132 should be stepped
down to 33 KV. It can very well be directly stepped down to
11 KV. If we have a dual reqmt of 33 as well as 11KV.
132/33/11KV( pri/sec/ter) can also be designed.
| Is This Answer Correct ? | 3 Yes | 0 No |
in indoor type circuit breakers why only the corner breaker trips specially during cold season. What is the reason.
Why we use a H.T. Fuse from a thick wire, on other side we use high rating of cables? & Why we use less Sq. mm Cable on H.T. side , on other side we use Large Sq. mm cable?
which stabilizer is better ? AVR, Servo Stabilizer, Static stabilizer etc & why explain it
What current flows in the transformer primary when its secondary is open?
For a spring controlled governer the relation F = ar+b (F is the controlling force, r is the radius of rotation a and b are constants), indicates that the governer is
Hi,, Just I want ask, if the power factor decrease what happen in voltage regulation? Thanks..
Where can I get CPWD electrical shedule rates in web? please help me.
How LT megger works ?
I have experienced electrical maintenance HT ,but I completed be ECE ....can I apply c license or not ???? Pls help me friend s...
can we use ac ameter as dc ameter with ct
A genarator is connected through a 20MVA ,13.8/138 KV stepdown transformer to a transmission line. at the reciving end of the line a load is supplied through a step down transformer of 10MVA,138/69 KV rating .A 0.72 PU load evaluated on load side transformer ratings as base values ,is supplied from the above system for system base values of 10 MVA and 69 KV in load circuit the value of the load in generator circuit will be ...........
define reflection method?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)