how to calculate the steel for beams and columns for tender
purpose? any formula have?
Answers were Sorted based on User's Feedback
Answer / santosh eppili
Generally the thumb rule is
for 100 Cum of concreting 10MT of steel is required.
More over this varies with the type of construction like for light structures it varies from 8-10MT
Med Str 9-12MT
High strength Structures(Industrial) 10-14MT of steel is reqd.
Is This Answer Correct ? | 16 Yes | 2 No |
Answer / afsar ansari
In Beams:2.5 % Volume of R.R.C.(Quantity)
In slabs:1 % Volume of R.R.C.(Quantity)
Is This Answer Correct ? | 9 Yes | 4 No |
Answer / naveen
If the drawings are available, then bar bending schedule is
prepared and the steel quantity is calculated. Depending on
different diameters of bar used the steel quantity can be
calculated. If the loads are given then depending on the
loads the steel value is calculated.
Is This Answer Correct ? | 14 Yes | 10 No |
Answer / kumar
Only previous project cosumtion recrod we can do it
Is This Answer Correct ? | 3 Yes | 11 No |
SHEAR FORCE AND BENDING MOMENT DIAGRAMS
what is education Cess.
to minimize budget cost of building , what can i do
what is the depth of a pile foundation??density of wood?? nominal mix ratios for different grades of concrete? effect of earthquake on structures? bending moment and shear force diagrams and also learn to find out the deflection..how is under water concreting done??
Please tell me about building work from begining
plz. how many times required for compacting subbgrade in road way & how many water required?
8. What do you find more useful in your present work – your education or your practical experience from previous jobs or traineeships?
During estimation of walls of superstructure...which unit we'll use with quantity.cube or square
why elongation index is not required for concreteing coarse aggregate..
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
What is difference between limit state and working stress method? How it is applies in building structure.
What is the specific weight of sand?