What is the accepted silt content in sand for concreting
purpose by volume method?
Answers were Sorted based on User's Feedback
Answer / j.pandiyarajan
it should not be more than 8% by its volume
| Is This Answer Correct ? | 9 Yes | 1 No |
Answer / manjunatha.h.s
3% by weight and 5% by volume.....as per IS-383-1978, and
IS-2386-part-3
| Is This Answer Correct ? | 4 Yes | 0 No |
Answer / santosh singh
8% is the correct answer as per cpwd specifictions
| Is This Answer Correct ? | 6 Yes | 5 No |
Answer / anand kumar
NOT MORE THAN 5% OF USED SAND EITHER VOLUME OR WEIGHT AS PER
IS 456:1978
| Is This Answer Correct ? | 2 Yes | 3 No |
undistributed samples are obtained by
What should be the PH value of water for irrigation purpose
What is ideal location for cube casting, RMC vehical at Ground Floor and Slab casting at 40th Floor
How much snowcem required per sq. Meter area
3 Answers Bhushan Power Steel,
What is the difference between stress and pressure
one litre of shuttering oil how much area covered the shuttering?
plz send me civil q papers of hpcl
what is the definition of stress& strain.
hi guys what happens if you are absent for a supplymentry exam?
why reinforcement is not provided at centre for beams r column
What is a BBS?Find out the cutting length for a 300*300 column with 40 mm cover?
21 Answers L&T, SSC,
5. Do you feel that your present employer estimates your full work potential? Are they pleased with your work performance?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)