Critical path tasks are those tasks that:
A. Have equal pessimistic, optimistic, and most likely estimated times
B. Have a float rime of zero
C. Have the same start date
D. Have multiple early start dates and early finish dates
No Answer is Posted For this Question
Be the First to Post Answer
You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are gathering the documentation of the product of the project. This might include all of the following except: A. Technical specifications B. Electronic files C. Programming plans D. Performance measurements
You are a project manager for the information technology division of a local satellite TV broadcasting company. This spring, the chief information officer for your company gave you the project to convert and upgrade all the PCs in the department to the latest release of a specific desktop application. Prior to this conversion, all manner of desktop software existed on machines throughout the company and had caused increasing problems with sharing files and information across the company. A lot of unproductive hours were spent typing information into several formats. This project came about as a result of which of the following? A. Technological advance B. Business need C. Customer request D. Legal requirement
You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following outputs except: A. Overall risk ranking for the project B. List of prioritized risks C. Inputs to other processes D. List of risks for additional analysis and management
What are the functions of project management tool?
You are preparing a cash flow analysis for a project the company is considering undertaking. The project's cost is $525,000, and expected cash inflows are $125,000 the first year and then $75,000 per quarter the second year and $100,000 per quarter after that. What is the payback period? A. 16 months B. 27 months C. 32 months D. 28 months
Write about organising and staffing in management.
0 Answers Mahatma Gandhi University,
Your project team is a close group all busily working on project activities. They're close to approaching the performing stage of Team Development. All six members must communicate frequently with each other. How many lines of communication are there? A. 12 B. 15 C. 18 D. 14
You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of: A. Crashing B. Fast trucking C. Resource leveling D. Adjusting the resource calendar
Which performance measurement tells us what the projected total cost of the project will be at completion? A. ETC B. CPI C. SPI D. EAC
What was the biggest challenge you faced in your project?
What are the different types of software risks?
The purpose of the Initiation process is to: A. Formally recognize the existence of a project or project phase B. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technological advances, or legal requirements C. Formally recognize the stakeholders of the project and identify them in the project charter D. Formally recognize the project sponsor and document his or her project goals