Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use:
A. Analogous estimating techniques
B. Bottom-up estimating techniques
C. Parametric modeling techniques
D. Computerized modeling techniques
No Answer is Posted For this Question
Be the First to Post Answer
You are the project manger for Xylophone Phonics. They produce children's software programs that teach basic reading and math skills. You're performing cost estimates for your project and don't have a lot of details yet. You will use which of the following techniques? A. Analogous estimating techniques, because this is a form of expert judgment that uses historical information from similar projects B. Bottom-up estimating techniques because this is a form of expert judgment that uses historical information from similar projects C. Monte Carlo Analysis, because this is a modeling technique that uses simulation to determine estimates D. Parametric modeling, because this is a form of simulation used to determine estimates
You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following is true? A. This is the result of working with teams of people from two different countries. B. This condition is known as culture shock. C. This is the result of jet lag and travel fatigue. D. This condition is known as global culturalism.
Your project is progressing as planned. The project team has comp up with a demo that the sales team will use when making presentations to perspective clients. You will do which of the following at your next stakeholder process. A. Report on the progress of the demo and note that it's a completed task B. Preview the demo for stakeholders and obtain their approval and sign-off C. Review the technical documentation of the demo and obtain approval and sign-off D. Report that the demo has been noted as a completed task in the information retrieval system
Your hardware vendor left you voicemail saying that a snowstorm in the Midwest will prevent your equipment from arriving on time. You identified a risk response for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy? A. Transference B. Acceptance C. Mitigation D. Avoidance
You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the product scope as the glitch changed the characteristics of the product. Which of the following is true? A. Changes to product scope are reflected in the project scope. B. Changes to product scope are reflected in the integrated change control plan. C. Changes to product scope are a result of changes to the product description. D. Changes to product scope are a result of corrective action.
If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.
how to handle project single handed?and what are the roles and responsibilities of a project leader?
Describe the 4 p’s in software project management.
You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.
Your selection committee meets on a semiannual basis. They've determined that projects must meet or exceed a specific profit limit in order to be accepted and prioritized on the project list. Which of the following is true? A. The selection committee has defined project selection criteria, which is a tool and technique of Initiation. B. The selection committee has defined project selection methods, which is a tool and technique of Initiation. C. The selection committee has defined project selection methods, which is an input to Initiation. D. The selection committee has defined project selection criteria, which is an input to Initiation.
You are a project manager for Cashiers Systems. Your company produces cashiering systems and software for the retail industry. Your customer has requested a change that will change the characteristics of the cashiering system. You've described the characteristics of the cashiering system using this tool and technique of the Integrated Change Control process: A. Product description B. Product analysis C. Decomposition D. Configuration management
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You have been invited to dinner with the prospective foreign business partners and their spouses upon your arrival. You know that all of the following are generally true except: A. You should spend time building relationships with your prospective foreign business partners before getting down to business. B. You should explain your company's rules, standards, and operating policies at your first meeting with the prospective foreign business partners. C. You should build an atmosphere of mutual trust and cooperation. D. You should respect the cultural differences you'll encounter when working with your prospective foreign business partners.