Which of the following is true regarding constraints and assumptions?
A. Constraints restrict the actions of the project team, and assumptions are considered true for planning purposes.
B. Constraints are considered true for planning purposes, and assumptions limit the options of the project team.
C. Constraints consider vendor availability and resource availability to be true for planning purposes. Assumptions limit the project teamwork within predefined budgets or time lines.
D. Constraints and assumptions are inputs to the Initiation process. They should be documented, as they will be used throughout the project Planning process.
No Answer is Posted For this Question
Be the First to Post Answer
Describe the 4 p’s in software project management.
As project manager, you know that all of the following are true concerning analogous estimating techniques except: A. It's a qualitatively based estimating technique. B. It's a top-down estimating technique. C. It's a tool and technique of Activity Duration Estimating and Cost Estimating. D. It’s a form of expert judgment.
You’ve just accepted a new project management assignment. The project is for a customer in a foreign country. You've requested a business analyst and two other project team members from the country the customer resides in to participate on your team. The remaining team members are from your country. You know that the best way to ensure the project team doesn’t get bogged down in cultural differences and hold up project progress is to: A. Perform team-building exercises using videoconferencing to allow team members to get to know each other and get to the performing stage of team development as soon as possible. B. Provide diversity training for all the team members to make them aware of cultural differences and teach them to function effectively as a team despite these differences. C. Establish your role as project manager as the first order of business and require compliance to company policies. D. Require project team members to read and sign the organization’s diversity policy.
You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC? A. 75 B. 50 C. 125 D. 150
You are a project manager for Uncle Sam's Flag Company. Your company has designed a new line of products featuring the American flag. Due to some unique circumstances, the products are in hot demand and the project sponsor has asked you to do whatever it takes to get this project completed early and make the products available. You are to add resources to the project. The sponsor agrees to pay the additional costs since time is now a critical factor. Which technique have you used? A. Crashing B. Resource leveling C. Fast tracking D. Resource loading
Theory Y managers believe which of the following? A. That people are motivated only by money, power, or position B. That people will perform their best if they're given proper motivation and expectations C. That people are motivated to achieve a high level of competency D. That people are motivated by expectation of good outcomes
You are the project manager for Lucky Stars Candies. You've identified the deliverables and requirements and documented them where? A. In the scope statement, which will be used as in input to the Scope Definition process B. In the scope definition document, which is used as an input to the Scope Planning process C. In the WBS, which is an output of the Scope Planning process D. In the WBS, which is a tool and technique of the Scope Definition process
Your company, Kick That Ball Sports, has appointed you project manager for their new Cricket product line introduction. This is a national effort, and all the retail stores across the country need to have the new products on the shelves before the media advertising blitz begins. The product line involves three new products, some with multiple deliverables. You are ready to create the WBS. Which of the following is true? A. The WBS should include the three new products and the advertising campaign as level two deliverables. B. The WBS should include the three new products as level two deliverables. C. The WBS should include the three new products as level two deliverables and the advertising campaign as a level three deliverable. D. The WBS should include the three new products and the advertising campaign as level three deliverables.
You know that change control systems are important as they describe how to submit change requests and document how to manage the change, track the status, and determine the management impacts of the change. Each of the following processes in the Controlling process group uses a change control system as one of its tools and techniques except: A. Integrated Change Control B. Quality Control C. Scope Change Control D. Schedule Control
You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time
Many times software delivery is late, why? Give reason.
Explain the Principals of Management
0 Answers Mahatma Gandhi University,